Erosion Control: Ewa Gentry vs Kaneohe

How do erosion control rules compare between Ewa Gentry, HI and Kaneohe, HI?

Ewa Gentry and Kaneohe have similar restriction levels.

Ewa Gentry, HI

Honolulu County

Heavy Restrictions

ROH Sec. 18A-1.6 requires approved erosion and sediment control plans for Ewa Gentry land-disturbing activities that need building, grading, stockpiling, or trenching permits.

View full Ewa Gentry rules β†’

Kaneohe, HI

Honolulu County

Heavy Restrictions

Kaneohe's steep Koolau-adjacent lots require an approved erosion and sediment control plan under ROH Sec. 18A-1.6 before any permitted land-disturbing work begins.

View full Kaneohe rules β†’

Key Facts Comparison

FactEwa GentryKaneohe
--

Highlighted rows indicate differences between cities.

Ewa Gentry FAQ

Do I need an erosion plan to build a backyard addition?

If your project requires a building, grading, or trenching permit and disturbs land, Sec. 18A-1.6 requires an approved erosion and sediment control plan.

Who enforces the erosion control plan?

The Department of Planning and Permitting reviews plans and inspects sites, and can issue stop work orders or fines for non-compliance.

Kaneohe FAQ

Do retaining wall projects need a plan?

If the project requires a grading or building permit, an erosion and sediment control plan is typically required.

What BMPs are common for windward lots?

Silt fencing, stabilized construction entrances, inlet protection, and rapid revegetation after grading are standard.