Expedited Solar Permitting: Los Angeles vs Palmdale

How do expedited solar permitting rules compare between Los Angeles, CA and Palmdale, CA?

Los Angeles and Palmdale have similar restriction levels.

Los Angeles, CA

Los Angeles County

Few Restrictions

Los Angeles Department of Building and Safety issues residential rooftop solar permits through the SolarAPP+ portal under California Government Code §65850.5 and SB-379, granting automated approval for code-compliant systems within minutes during business hours.

View full Los Angeles rules →

Palmdale, CA

Los Angeles County

Few Restrictions

California Government Code §65850.5 and LA County Code Title 22.140.500 require expedited solar permitting for residential rooftop systems under 38.4 kilowatts. LA County uses SolarAPP+ instant online plan review through Building and Safety, typically issuing permits within three business days.

View full Palmdale rules →

Key Facts Comparison

FactLos AngelesPalmdale
Approval timeMinutes via SolarAPP+-
System size capUp to 38.4 kW DC-
Required licenceHomeowner or C-46 contractor-
Plan-check feeReduced or waived-
InspectionStill required after install-
Permit timeline-Three business days typical
Plan review-SolarAPP+ instant approval
Residential cap-38.4 kilowatts ministerial
Fee ceiling-500 dollars residential
State authority-Government Code §65850.5

Highlighted rows indicate differences between cities.

Los Angeles FAQ

How fast can I get a solar permit in Los Angeles?

Code-compliant residential systems under 38.4 kW DC are approved in minutes through LADBS Solar Express (SolarAPP+) during business hours, with the permit issued automatically before installation begins.

Does SolarAPP+ cover battery storage?

Yes. LADBS accepts SolarAPP+ submissions for solar PV with paired battery storage on single-family homes. Stand-alone batteries or larger commercial systems require regular plan-check review.

Palmdale FAQ

How long does a residential solar permit take in unincorporated LA County?

SolarAPP+ approves compliant plans the same day; standard permits issue within three business days. Inspection follows installation within five business days. Total project timeline from contract to operation usually runs four to six weeks.

Can the County require design review or HOA-style approval?

No. Government Code §65850.5 prohibits discretionary review, aesthetic conditions, or hearings for code-compliant residential rooftop solar under 38.4 kilowatts. The permit must be ministerial and use a checklist only.

Compare other topics

See how Los Angeles and Palmdale compare on other ordinance categories.

Want to add a third city?

Use our full comparison tool to compare up to three cities.

Open Comparison Tool