Key Facts

Buffer zone
100 ft from protected resource areas
Governing sections
Boston Code § 7-1.4(C), (G)(7), (J)
Enforcing body
Boston Conservation Commission
Permit required
order of conditions before work starts
Permit term
3 years, extendable up to 3 more
Penalty structure
per-day, per-area separate offenses

Summary

Construction and other regulated activity within 100 feet of Boston wetlands, streams, ponds, or the coast falls under Conservation Commission buffer-zone review, and Code § 7-1.4(G)(7) lets the Commission impose erosion and sedimentation design specifications, performance standards, and setbacks before work can proceed.

In reviewing activities within the buffer zone, the Commission shall presume the buffer zone is important to the protection of other resource areas because activities undertaken in close proximity have a reasonable probability of adverse impact, either immediately, as a consequence of construction, or over time, as a consequence of daily operation or existence of the activities. These adverse impacts from construction and use can include, without limitation, erosion, siltation, loss of groundwater recharge, poor water quality, loss of wildlife habitat, degradation of wetland plant habitat, alteration of hydrology and proliferation of invasive plants. The Commission may establish, in its regulations, design specifications, performance standards and other measures and safeguards, including setbacks, and other work limits for protection of such lands, including without limitation strips of continuous, undisturbed vegetative cover, unless the Commission determines, based on adequate evidence, that the buffer zone or part of it may be altered without harm to the values protected by the ordinance.

Source: EPA NPDES Construction General PermitView official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: 2026 S-2: Current through Ordinance 2025 C. 14, passed 11-5-2025).

Full Breakdown

4(C)(1)(b) puts "lands adjoining these resource areas out to a distance of 100 feet, known as the buffer zone," within Conservation Commission jurisdiction. either immediately, as a consequence of construction, or over time," including erosion, siltation, loss of groundwater recharge, and degraded water quality. Under (G)(7), when reviewing buffer-zone work the Commission presumes the buffer zone is important precisely because of these construction-phase risks, and "may establish, in its regulations, design specifications, performance standards and other measures and safeguards, including setbacks, and other work limits," up to and including requiring strips of continuous, undisturbed vegetative cover, unless the applicant shows the area can be altered without harm.

To trigger review, an applicant files a written notice of intent by certified mail or hand delivery under (E), including plans showing the work's environmental effects and a Commission-set filing fee on top of the state Wetlands Protection Act fee; no work may start until the Commission issues an order of conditions and appeal periods run. A permit is valid three years and may be extended once for up to three more. This buffer-zone erosion-control authority applies only within jurisdictional resource areas and their 100-foot buffer, riverfront areas, and the Coastal and Inland Flood Resilience Zones, not to construction sites generally.

Violations & Fines

Enforcement runs through § 7-1.4(J): the Commission and its agents can enter land to inspect, and may enforce through violation notices, fines it sets itself, noncriminal citations under M.G.L. Chapter 40, Section 21D, and civil or criminal court action pursued by Corporation Counsel or the Police. Each day a violation continues, and each resource area or buffer zone affected, counts as a separate offense, and violators can be ordered to restore the land to its original condition.

Frequently Asked Questions

Does Boston regulate erosion control for construction near wetlands?
Yes. Code § 7-1.4 gives the Conservation Commission jurisdiction over any activity within 100 feet of a protected resource area, the buffer zone, where erosion, siltation, and hydrology changes are presumed to threaten wetland values, letting the Commission impose design specs and setbacks before work proceeds.
What can the Commission require to control erosion on a project site?
Under § 7-1.4(G)(7), the Commission may set design specifications, performance standards, work limits, and setbacks, including requiring strips of continuous, undisturbed vegetative cover, unless it finds the buffer zone can be altered without harming protected wetland values.
How do I apply for buffer-zone work in Boston?
File a written notice of intent with the Conservation Commission by certified mail or hand delivery, including plans showing the proposed work's environmental effects; work cannot start until the Commission issues an order of conditions and all appeal periods expire, under § 7-1.4(E).
What happens if I disturb a buffer zone without a permit?
Enforcement under § 7-1.4(J) treats each day of a continuing violation, and each affected resource area or buffer zone, as a separate offense. The Commission sets and levies fines, can order restoration of the land, and may pursue noncriminal citations or civil and criminal court action.

Sources & Official References

Other rules in Boston

All Boston rules

Compare Boston to another location·View the Massachusetts environmental rules overview

Get notified when Erosion Control in Boston, MA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Erosion Control in Nearby Cities

How other cities in this county handle erosion control.

Chelsea, MA
Some Restrictions
Revere, MA
Some Restrictions