St. Louis County, MO Building Safety: Building Permits (2026)
Key Facts
- Permit trigger
- Any construction, alteration, demolition, occupancy change
- Shed exemption
- Exempt only up to 120 sq ft
- Permit expiration
- 180 days if work not started
- Application abandonment
- 180 days unpursued equals abandoned
- Issuing office
- Building official, Dept. of Transportation & Public Works
Summary
St. Louis County requires a building permit before almost any construction, alteration, demolition, or occupancy change under Section 105.1 of the Building Code, whether the work involves a structure, a paved parking lot serving more than one single-family dwelling, or a new lot line affecting an existing building. Section 105.2 carves out a short, narrow list of exemptions.
105.1 Required. Any owner or owner's authorized agent who intends to construct, enlarge, alter, repair, move, demolish, or change the occupancy of a building or structure, or install or alter a ground level paved parking lot other than those lots serving a single-family dwelling, or establish a new or relocated lot line that affects an existing structure, or to erect, install, enlarge, alter, repair, remove, convert or replace any electrical, gas, mechanical or plumbing system, the installation of which is regulated by this code, or to cause any such work to be performed, shall first make application to the building official and obtain the required permit. ... 105.2 Work exempt from permit. ... Permits shall not be required for the following: Building: 3. One-story detached accessory structures used as tool and storage sheds, playhouses and similar uses, provided the floor area does not exceed 120 square feet (11.15 m2). ... 9. Movable cases, counters and similar fixtures not over 5 feet 9 inches (1753 mm) in height.
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 85 | Traffic: Supplement 80).
Full Breakdown
1 casts a wide net: any owner or authorized agent who intends to construct, enlarge, alter, repair, move, demolish, or change the occupancy of a building or structure needs a permit before starting, and the same rule reaches paved parking lots other than those serving a single-family dwelling, new or relocated lot lines that affect an existing structure, and any electrical, gas, mechanical or plumbing system regulated by the code. 3 lets the official authorize an early start at the applicant's own risk. 2 lists the work that does not need a permit, though the exemption is narrow.
A one-story detached shed, playhouse or similar accessory structure is exempt only if its floor area stays at 120 square feet or under; movable cases, counters and similar fixtures are exempt only below 5 feet 9 inches in height; and ordinary finish work like painting, papering or installing cabinets and countertops never needed a permit in the first place. Every other item on the exemption list, covering fences, retaining walls, small pools and window awnings, carries its own separate size or height ceiling that this general permit section does not replace.
5 gives the work 180 days to start and requires it to stay active, with an automatic lapse if work is suspended for 180 days after it begins; the building official can grant one or more 180-day extensions on written request with justifiable cause. 2, and the county gives 14 days' written notice before destroying the plans on file.
Violations & Fines
Starting construction, a paved parking lot, or a change of occupancy without first obtaining the permit required by Section 105.1 exposes the owner to a stop work order and the misdemeanor penalties set out elsewhere in the Building Code, including the possibility of the county withholding future permits under Section 105.3.1.1 until unpaid fees or unresolved violations are cleared. Letting an issued permit lapse under Section 105.5 without requesting an extension means the work has to restart the permit process from scratch.
Frequently Asked Questions
Do I need a permit to build a small storage shed in St. Louis County?
How long is a St. Louis County building permit valid once issued?
What happens if I never pick up my building permit application?
Sources & Official References
Other rules in St. Louis County
Compare St. Louis County to another location·View the Missouri building safety overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.