Summary
Okaloosa County requires a permit under Sec. 6-134(b) before anyone builds, enlarges, alters, repairs, moves or demolishes a building or structure, or installs electrical, gas, mechanical or plumbing systems the technical codes regulate. Starting covered work before the permit issues draws a penalty equal to 100 percent of the normal permit fee.
(b)A permit is required when:(1)An owner, authorized agent or contractor desires to construct, enlarge, alter, repair, move, demolish, or change the occupancy of a building or structure. As used herein, the term building means a roofed and/or walled structure enclosing a space used for sheltering any occupancy. As used herein, a structure is anything constructed or erected with fixed location on the ground, measuring 30 inches above natural grade. A structure may be a building, deck, sign, billboard, liquid storage tank, antenna or tower.(2)An owner, authorized agent or contractor desires to erect, enlarge, alter, repair, remove, convert, or replace any electrical, gas, mechanical, or plumbing system, the installation of which is regulated by the technical codes.(d)Work commencing prior to permit issuance. Any person commencing any work on a building, structure, electrical, gas, mechanical, plumbing or underground utility system before obtaining the necessary permit(s) shall be subject to a penalty of 100 percent of the usual permit fee in addition to the required permit fees.
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 23).
Full Breakdown
Sec. 6-134(b) of the county code lays out when Okaloosa County's Growth Management Department requires a building permit. The first trigger covers any owner, authorized agent or contractor who wants to construct, enlarge, alter, repair, move, demolish or change the occupancy of a 'building', defined broadly as any roofed and/or walled structure enclosing a space used for sheltering an occupancy, or a 'structure', defined even more broadly as anything erected with a fixed location on the ground measuring 30 inches or more above natural grade, expressly including a deck, sign, billboard, liquid storage tank, antenna or tower, not just a conventional building.
The second trigger covers electrical, gas, mechanical or plumbing system work regulated by the technical codes, meaning most system installations or alterations need their own permit even when no structural work is involved. A third, separate trigger applies to underground utility systems, which require plans, permitting and inspection from three county departments at once: Growth Management, Water and Sewer, and Public Works. 721, Florida Statutes, plus non-county costs like credit card processing charges. If work starts before the permit is obtained, subsection (d) imposes a penalty equal to 100 percent of the usual permit fee, on top of that fee, and subsection (e) lets the building official deny or recalculate the permit if the declared project value looks underestimated.
Violations & Fines
Commencing any building, structure, electrical, gas, mechanical, plumbing or underground utility work before the required permit is issued triggers a penalty equal to 100 percent of the standard permit fee, charged in addition to the fee itself under Sec. 6-134(d). The building official can also deny or recalculate a permit application whose declared value appears underestimated, and both the permit holder and the property owner remain responsible for compliance with every adopted code.
Frequently Asked Questions
Does a backyard shed need a building permit in Okaloosa County?
What happens if I start construction before pulling a permit?
Why do underground utilities need three different departments to sign off?
Sources & Official References
Other rules in Okaloosa County
Florida rules heatmap·Compare Okaloosa County to another location·View the Florida building safety overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.