Key Facts

Permit trigger
Any construction, alteration, repair, or demolition
Minor-work exemption
$5,000 or less, single-family or farm building only
Plans required
Estimated cost over $20,000
Licensed contractor required
Estimated cost over $20,000
Permit expiration
6 months unstarted; 12 months if halted
Enforcing agency
County Inspection Department, building inspector

Summary

Sec. 11-81 of the county code bars anyone from constructing, reconstructing, altering, repairing, moving, or demolishing a building in the unincorporated county without first securing a permit from the inspection department, and Sec. 11-84 requires a licensed general contractor and, in some cases, a registered architect or engineer's seal once the estimated cost exceeds $20,000.

City-specific rules exist: Wilmington has its own building permits rules that differ from New Hanover County's county-level regulations. If you live in Wilmington, check the city-specific page instead.

(a)No person may commence or proceed with:(1)The construction, reconstruction, alteration, repair, movement to another site, removal, or demolition of any building; ... without first securing from the inspection department with jurisdiction over the site of the work each permit required by the state building code and any other state or local law or local ordinance or regulation applicable to the work. ... (a)No building permit shall be issued for any building or structure the estimated total cost of which is more than $20,000.00 unless the work is to be performed by a licensed general contractor.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 15 Update 1).

Full Breakdown

Sec. 11-81(a)(1) makes it unlawful to commence or proceed with the construction, reconstruction, alteration, repair, movement, removal, or demolition of any building in the unincorporated county without first securing every permit required by the state building code and any applicable local ordinance from the inspection department with jurisdiction over the site. The exemption for work costing $5,000 or less in a single-family residence or farm building does not cover additions or changes to load-bearing structures, plumbing, heating, air conditioning, electrical wiring, or roofing beyond same-grade replacement (Sec.

11-81(a)). Written applications go on forms from the inspection department and must show the owner's name and address, any authorized agent, and the contractor's name with proof of the required state licensing-board certificate (Sec. 11-82). Detailed, scaled plans and specifications must accompany any application where the estimated cost exceeds $20,000, or whenever the inspector deems them necessary (Sec. 11-83). No permit for a project over $20,000 may issue unless a licensed general contractor performs the work, and, for buildings other than one- or two-family dwellings over that threshold, unless the plans bear a registered architect's or engineer's state seal (Sec.

11-84). No permit for alteration, repair, or construction may issue unless the plans show compliance with the county zoning ordinance (Sec. 11-85), and the county may withhold a permit from a subdivider who has failed to comply with subdivision or development conditions (Sec. 11-86(b)). Building permit fees follow the schedule kept in the building inspector's office (Sec. 11-87(1)). A permit expires six months after issuance if work has not begun, and immediately if work stops for 12 months (Sec. 11-88); the inspector may also revoke a permit for a substantial departure from approved plans or a false statement made to obtain it (Sec. 11-90).

Violations & Fines

Building without a required permit, or after revocation, falls under the county's general penalty, Sec. 1-6: a misdemeanor punishable per G.S. 14-4, with each day of continuing violation charged as a separate offense. The inspector can issue a written stop order under Sec. 11-47 halting hazardous or noncompliant work immediately, appealable to the state insurance commissioner within five days, and may revoke the permit under Sec. 11-90 for false statements or a substantial departure from the approved plans.

Frequently Asked Questions

When do I need a building permit in unincorporated New Hanover County?
Sec. 11-81 requires a permit before you construct, reconstruct, alter, repair, move, remove, or demolish any building in the unincorporated county. A narrow exemption covers repairs costing $5,000 or less on a single-family residence or farm building, but it does not cover load-bearing, plumbing, electrical, HVAC, or roofing changes.
Do I need an architect or licensed contractor for my project?
Once the estimated cost tops $20,000, Sec. 11-84 requires the work to be performed by a licensed general contractor, and, for anything other than a one- or two-family dwelling, requires the plans to bear a registered architect's or engineer's state seal.
How long does a New Hanover County building permit last?
Under Sec. 11-88, the permit expires six months after issuance if you have not started the authorized work. If you start and then stop for 12 months, the permit expires immediately and you must obtain a new one before resuming.

Sources & Official References

Other rules in New Hanover County

All New Hanover County rules

Compare New Hanover County to another location·View the North Carolina building safety overview

Get notified when Building Permits in New Hanover County, NC changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Building Permits in Cities Across New Hanover County