Key Facts

Permit trigger
Any construction, alteration, repair, demolition or occupancy change
Shed exemption
Detached accessory structures 200 sq ft or less
Flat residential permit fee
$125 for most trades/additions
New building permit fee
Folded into plan review charge
Permit expiration
180 days without starting work
Violation fine range
$100-$500 (Sec. 8:1303)

Summary

Sec. 8:500 requires any owner planning to build, enlarge, alter, repair, move, demolish or change the occupancy of a structure to get a City-Parish building permit first. Sec. 8:501 exempts a short list of small jobs. Permits lapse after 180 days of inactivity, and violations run $100 to $500.

These county ordinances apply to unincorporated areas of East Baton Rouge Parish. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

Sec. 8:500. - Permit required. Any owner or owner's authorized agent who intends to construct, enlarge, alter, repair, move, demolish or change the occupancy of a building or structure, or to erect, install, enlarge, alter, repair, remove, convert or replace any electrical, gas, mechanical or plumbing system, the installation of which is regulated by this title, or to cause any such work to be performed, shall first make application to the building official and obtain the required permit. ... Exemptions from permit requirements of this title shall not be deemed to grant authorization for any work to be done in any manner in violation of the provisions of this title or any other laws or ordinances of this jurisdiction. Permits shall not be required for the following: (1) Building. a. One-story detached accessory structures used as tool and storage sheds, playhouses and similar uses, provided the floor area is not greater than two hundred (200) square feet.

Full Breakdown

East Baton Rouge Parish's building-permit trigger is broad: Sec. 8:500 requires any owner or authorized agent who intends to construct, enlarge, alter, repair, move, demolish or change the occupancy of a building or structure, or to install, alter, repair, remove, convert or replace an electrical, gas, mechanical or plumbing system, to first apply to the building official and obtain a permit. Sec. 8:501 then carves out a list of specific small-scale exemptions that need no permit at all, including one-story detached accessory structures like tool sheds and playhouses under 200 square feet, on-grade water tanks holding 5,000 gallons or less, ordinary painting and finish work such as tiling and cabinetry, temporary movie and stage sets, and small prefabricated swimming pools under 24 inches deep.

Sec. 8:501 makes clear an exemption from the permit requirement does not excuse compliance with the underlying building standards or any other ordinance. Under Sec. 8:801(5), most other residential permits, including additions, renovations, generators, pools, fences, solar installs and driveways, carry a flat $125 fee, while a new residential building permit fee is folded into the plan review charge. Commercial work is billed on a sliding per-$1,000-of-valuation scale under Sec. 8:801(3). Once issued, Sec. 8:509 voids a permit if work has not started within 180 days, or is suspended for 180 days after starting, subject to written extensions from the building official. Sec. 8:511 requires the permit be posted and kept visible at the jobsite for the duration of the project.

Violations & Fines

Building without the required permit, or departing from the approved construction documents or a building official's directive, violates Sec. 8:1300 and Sec. 8:1303, carrying a fine of not less than $100 nor more than $500. The building official can serve a notice of violation under Sec. 8:1301 ordering the work stopped and the condition abated, and refer the matter for prosecution under Sec. 1:609 et seq. of Title 1 if the notice is not complied with.

Frequently Asked Questions

What triggers a building permit in East Baton Rouge Parish?
Sec. 8:500 requires a permit before you construct, enlarge, alter, repair, move, demolish or change the occupancy of a building or structure, or before you install, alter or replace an electrical, gas, mechanical or plumbing system regulated by the technical codes.
What work is exempt from a building permit?
Sec. 8:501 exempts one-story accessory sheds and playhouses under 200 square feet, on-grade water tanks of 5,000 gallons or less, ordinary finish work like painting and tiling, temporary movie sets, and small prefabricated pools under 24 inches deep. None of these exemptions excuse compliance with the underlying building standards.
How much does a residential building permit cost?
Sec. 8:801(5)(b) sets most residential permits, covering additions, renovations, generators, pools, fences, solar and driveways, at a flat $125, while the new-building permit fee is included in the plan review charge instead of billed separately.
How long is a permit good for once issued?
Sec. 8:509 voids a permit if the authorized work is not started within 180 days of issuance, or is suspended for 180 days once begun. The building official can grant written extensions of up to 180 days at a time for justified delays.

Sources & Official References

Other rules in East Baton Rouge Parish

All East Baton Rouge Parish rules

Compare East Baton Rouge Parish to another location·View the Louisiana building safety overview

Get notified when Building Permits in East Baton Rouge Parish, LA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Building Permits in Cities Across East Baton Rouge Parish