Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified August 2026

Key Facts

Permit required for
construct, alter, repair, move, demolish
Also covers
electrical, gas, mechanical, plumbing systems
Applies in
unincorporated Brevard County only
Application expires
6 months if permit not issued
Minor mechanical exemptions
portable heaters, coolers, small refrigeration units

Summary

Unincorporated Brevard requires a building permit before you construct, alter, repair, move, or demolish a structure, or touch its electrical, gas, mechanical, or plumbing systems.

City-specific rules exist: Cocoa, Palm Bay, and Titusville have their own building permits rules that differ from Brevard County's county-level regulations. If you live in one of those cities, check the city-specific page instead.

Any owner, authorized agent, or contractor who desires to construct, enlarge, alter, repair, move, demolish, or change the occupancy or occupant content of a building or structure...or to erect, install, enlarge, alter, repair, remove, convert or replace any electrical, gas, mechanical or plumbing system...shall first make application to the building official and obtain the required permit for the work.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 135).

Full Breakdown

The county adopted a stricter Florida Building Code administration chapter for unincorporated Brevard. Under it, any owner, agent, or contractor who wants to construct, enlarge, alter, repair, move, demolish, or change the occupancy of a building or structure, or to install or replace an electrical, gas, mechanical, or plumbing system, must first apply to the Building Official and obtain a permit before starting work. Minor mechanical items like portable heaters, portable coolers, and small self-contained refrigeration units under 10 lbs of refrigerant are exempted, as are ordinary minor repairs the Building Official approves. Applications expire 6 months after filing if no permit issues, with 90-day extensions available for justifiable cause.

Violations & Fines

Working without a required permit lets the Building Official issue a stop-work order and revoke or withhold future permits; unpermitted work found later must be brought into code compliance or removed.

Frequently Asked Questions

Do I need a permit to repair my roof in unincorporated Brevard?
Yes. Repair is one of the listed permit triggers under Sec. 22-47's Section 104.1.1, unless the Building Official approves it as an ordinary minor repair.
Does this apply inside Cocoa, Titusville, or Melbourne?
No. This chapter governs only unincorporated Brevard County; those cities enforce their own adopted building codes.
How long is a Brevard building permit application valid before it expires?
An application is deemed abandoned and expires 6 months after filing if no permit has been issued, though 90-day extensions are available for justifiable cause.

Sources & Official References

Other rules in Brevard County

All Brevard County rules

Florida rules heatmap·Compare Brevard County to another location·View the Florida building safety overview

Get notified when Building Permits in Brevard County, FL changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Building Permits in Cities Across Brevard County