Marin County, CA Building Safety: Electrical Permits (2026)
Key Facts
- Adopted code
- 2025 California Electrical Code, Title 24 Part 3
- Base standard
- 2023 National Electrical Code (NFPA)
- Enforcing agency
- CDA Building and Safety Division
- Application expires
- 1 year if permit not issued
- Permit voids
- Work not done in 2 years
- Penalty
- 2 to 4 times the permit fee
- Appeal fee
- $120 to Board of Appeals
Summary
Marin County Code Section 19.04.010 adopts the 2025 California Electrical Code, which incorporates the 2023 National Electrical Code, as the standard governing all electrical permits in the unincorporated county. The Building and Safety Division of the Community Development Agency reviews plans, issues permits, and inspects electrical work under this adopted code.
(3)The 2025 edition of the California Electrical Code, known as California Code of Regulations, Part 3 of Title 24, incorporating the 2023 edition of the "National Electrical Code" published by the National Fire Protection Association, with exceptions, additions and deletions as provided in this title.
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Municipal Code: Supplement 2026 Update 1).
Full Breakdown
Under Marin County Code Section 19.04.010(3), the county has adopted the 2025 edition of the California Electrical Code, California Code of Regulations Title 24 Part 3, which in turn incorporates the 2023 National Electrical Code published by the National Fire Protection Association, subject to local exceptions, additions, and deletions set out in Title 19. Section 19.04.012 substitutes county terminology throughout the adopted code: wherever the code says 'city' it means 'county,' and 'building official' means the Marin County building official.
The Building and Safety Division, established under Section 19.04.020, handles plan review, permit issuance, fee collection, and inspection of electrical installations for the unincorporated territory. Permit fees follow the Master Fee and Service Schedule adopted under Section 19.04.032, with a technology enhancement surcharge of six percent of the permit fee and a discount of up to sixty percent when an applicant uses a pre-approved third-party plan-check or inspection service. An electrical permit application expires if the permit itself is not issued within one year of the application under Section 19.04.050, and an issued permit becomes void if work has not substantially commenced within one year, or is not completed within two years, under Section 19.04.055. The building official may grant extensions of between seven and three hundred sixty-five days upon a written, justified request and payment of an extension fee. Appeals of building-official decisions go to the county's Board of Appeals for a $120 filing fee set under Section 19.04.032(d)(10).
Violations & Fines
Working without a required electrical permit, or violating any provision of the adopted Electrical Code, is a separate offense for each day the violation continues under Section 19.04.029. Conviction carries a fine equal to two to four times the permit fee that would have applied to legalize the work, calculated from the Section 19.04.032 fee schedule, unless the agency director waives it for prompt correction.
Frequently Asked Questions
What electrical code applies to unincorporated Marin County?
Who issues electrical permits in unincorporated Marin County?
How long is an electrical permit application valid before I get the permit?
What is the penalty for doing electrical work without a permit in Marin County?
Sources & Official References
Other rules in Marin County
California rules heatmap·Compare Marin County to another location·View the California building safety overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.