Key Facts

Adopted code
2023 National Electrical Code, WCC § 100.100.10(11)
Permit issuance fee
$45.00 flat (Appendix A, Table 8)
New single-family wiring fee
$0.04 per square foot
Multifamily wiring fee
$0.03 per square foot
Unpermitted work penalty
2x to 4x fee, up to $4,000 residential
Enforcing agency
Washoe County Building Program

Summary

Washoe County requires a permit before anyone installs, alters, or replaces an electrical system, per Washoe County Code § 100.105.1. The Building Program inspects that work against the 2023 National Electrical Code, adopted at § 100.100.10(11). Permit issuance costs $45, plus per-square-foot fees for new wiring under Appendix A, Table 8, and unpermitted work is a misdemeanor with a doubled inspection fee.

City-specific rules exist: Reno has its own electrical permits rules that differ from Washoe County's county-level regulations. If you live in Reno, check the city-specific page instead.

100.105.1 - Required. Any owner or authorized agent who intends to construct, enlarge, alter, repair, move, demolish, or change the occupancy of a building or structure, or to erect, install, enlarge, alter, repair, remove, convert or replace any electrical, gas, mechanical or plumbing system, the installation of which is regulated by this code, or to cause any such work to be done, shall first make application to the Building Program and obtain the required permit. 100.100.10 - Adopted codes. The following recognized codes are hereby adopted by Washoe County together with the supplements, listed changes, additions and deletions as noted: ... 11.2023 National Electrical Code ("NEC First Print").

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 20 Update 2).

Full Breakdown

Section 100.105.1 of the Washoe County Code requires anyone who intends to erect, install, enlarge, alter, repair, remove, convert or replace an electrical system to first apply to the Building Program and obtain a permit before starting work. The county adopted the 2023 National Electrical Code as item 11 of § 100.100.10's list of adopted codes, most recently amended by Ordinance No. 1736 effective July 1, 2025. A handful of minor jobs are exempt under § 100.105.2: replacing lamps, connecting approved portable equipment to existing receptacles, reinstalling attachment plug receptacles, swapping a branch circuit overcurrent device of the same capacity in the same location, repairing switches or control devices, replacing electrodes or transformers of the same size for signs, and replacing light fixtures in single-family homes and accessory structures. Listed temporary decorative or construction lighting, carnival wiring, and lab experimental wiring are also exempt. Everything else needs a permit and inspection.

Fees run from Appendix A, Table 8: $45 to issue any electrical permit, plus a system fee of $0.04 per square foot for new single- and two-family wiring, $0.03 per square foot for new multifamily wiring, $15 for a private in-ground residential pool's electrical work, and $15 for a temporary power pole. Applicants who need work done before a permit issues, such as an emergency repair, must submit the application by the next business day under § 100.105.1.1, and contractors who regularly perform repeat alteration work can apply for an annual permit instead of filing one application per job under § 100.105.1.2.

Violations & Fines

Performing electrical work without the required permit is an unlawful act under § 100.113.1 and is prosecuted as a misdemeanor, with each day of continued violation charged as a separate offense under § 100.113.3. Anyone who starts work before a permit issues owes an investigative fee equal to double the permit fee under § 100.113.3.1, which the Building Program can raise to four times the fee for a licensed contractor, capped at $4,000 for residential work. The Division Director can also issue a stop work order under § 100.114.1.

Frequently Asked Questions

Do I need a permit for minor electrical repairs in Washoe County?
No. Washoe County Code § 100.105.2 exempts minor repairs such as replacing lamps, reinstalling attachment plug receptacles, swapping a branch circuit breaker of the same capacity in the same location, and replacing light fixtures in single-family homes. Anything beyond that, including new circuits, panel upgrades, or rewiring, needs a permit from the Building Program before work starts.
What electrical code does Washoe County enforce?
The county enforces the 2023 National Electrical Code, adopted as item 11 of Washoe County Code § 100.100.10 along with the Northern Nevada Amendments published by the Northern Nevada Chapter of the International Code Council. The current adoption ordinance, Ordinance No. 1736, took effect July 1, 2025, and the Building Program inspects all permitted work against that edition.
How much does a new home electrical permit cost in Washoe County?
Appendix A, Table 8 sets a $45 issuance fee plus a system fee of $0.04 per square foot of floor area for a new single- or two-family home, or $0.03 per square foot for a new multifamily building. A private in-ground pool's electrical work adds a flat $15, and a temporary power pole for a construction site is another $15.
What happens if I do electrical work without a permit in Washoe County?
It is a misdemeanor under § 100.113.1, and the Building Program charges an investigative fee equal to double the permit fee under § 100.113.3.1, which can rise to four times the fee, up to $4,000, for a licensed contractor who worked before permitting. Each day the violation continues counts as a separate offense, and the county can issue a stop work order.

Sources & Official References

Other rules in Washoe County

All Washoe County rules

Compare Washoe County to another location·View the Nevada building safety overview

Get notified when Electrical Permits in Washoe County, NV changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Electrical Permits in Cities Across Washoe County