Key Facts

Governing section
Clackamas County Code § 9.02.040(D)
Adopted code
Oregon Electrical Specialty Code, OAR 918-251
Residential permit base fee
$277 up to 1,000 sq ft
Permanent service fee range
$165 to $907 by amperage
Added plan review
25% of permit fee for high-risk work

Summary

Clackamas County enforces the Oregon Electrical Specialty Code as part of its own Building Code, so any new wiring, service upgrade or electrical alteration in the unincorporated county needs a county electrical permit. Fees run from $112 for a service reconnect to $907 for a permanent service over 1,000 amps.

These county ordinances apply to unincorporated areas of Clackamas County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

D. The Oregon Electrical Specialty Code, as adopted by OAR Chapter 918, Division 251 except as modified in this Chapter, shall be enforced as part of this Chapter.

E. The Oregon Residential Specialty Code, as adopted by OAR Chapter 918, Division 480, except as modified in this Chapter, shall be enforced as part of this Chapter.

F. The manufactured dwelling park and mobile home park rules adopted by OAR Chapter 918 Division 600, except as modified in this Chapter, shall be enforced as part of this Chapter.

G. The manufactured structure rules adopted by OAR Chapter 918, Division 500, except as modified in this Chapter, shall be enforced as part of this Chapter.

H. The Recreational Park and Organizational Camp Rules adopted by OAR Chapter 918, Division 650, except as modified in this Chapter, shall be enforced as part of this Chapter.

I. Chapter 9.01 of the Clackamas County Code: Code for the Abatement of Dangerous Buildings and Structures.

J. Chapter 9.03 of the Clackamas County Code: Excavation and Grading.

K. The On-Site Sewage Disposal Rules as adopted by OAR Chapter 340, Division 71 and OAR Chapter 340, Division 73, except as modified in this Chapter, shall be enforced as part of this Chapter.

L. The Oregon Energy Efficiency Specialty Code as adopted by OAR Chapter 918, Division 460, except as modified in this Chapter, shall be enforced as part of this Chapter.

Full Breakdown

310: the Building Official reviews the application before issuing a permit, and the permit holder must request every required inspection. Appendix A's Electrical Fees schedule sets the numbers: a residential single- or multi-family dwelling unit up to 1,000 square feet, including attached garages, is $277, with $56 for each additional 500 square feet. Permanent service or feeder installations run from $165 for under 200 amps to $907 for over 1,000 amps, and temporary construction service follows its own scale from $96 to $907. 25 for each additional circuit, and limited-energy systems such as alarm and low-voltage wiring installed with the same permit run $112.

Electrical plan review, an added 25% of the permit fee, is required under OAR 918-311-0040 for higher-risk work such as services rated 400 amps or more with high fault current, 150 KVA or larger separately derived systems, fire pump or emergency system installations, buildings over three stories or 10,000 square feet, and occupant loads over 99 persons.

Violations & Fines

Performing electrical work without the required permit exposes the owner or contractor to an investigation under Section 9.02.280 and an investigation fee in addition to the eventual permit fee, whether or not a permit is issued afterward. The Building Official can refuse further permits or occupancy approval for the property under Section 9.02.260 while an electrical violation remains outstanding, and the county can pursue injunction, abatement or other enforcement under Section 9.02.330.

Frequently Asked Questions

Does Clackamas County require its own electrical permit?
Yes. Section 9.02.040(D) enforces the Oregon Electrical Specialty Code as part of the county's own Building Code, and electrical work goes through the same application and inspection process under Sections 9.02.240 and 9.02.310 as any other building permit in the unincorporated county.
How much does a residential electrical permit cost?
Appendix A sets a residential single- or multi-family dwelling electrical permit at $277 for up to 1,000 square feet of dwelling and attached garage space, with $56 added for each additional 500 square feet. Service or feeder fees are separate and scale with amperage, from $165 to $907.
What electrical work needs extra plan review?
Under OAR 918-311-0040, work such as a 400-amp-or-larger service with high fault current, a 150 KVA or larger separately derived system, fire pump or emergency system installations, buildings over three stories or 10,000 square feet, and occupant loads over 99 persons require plan review at 25% of the permit fee.
What happens if I skip the electrical permit?
The county can open an investigation under Section 9.02.280 and charge an investigation fee on top of whatever permit fee eventually applies, and the Building Official can withhold other permits or occupancy approval for the property under Section 9.02.260 until the violation is resolved.

Sources & Official References

Other rules in Clackamas County

All Clackamas County rules

Compare Clackamas County to another location·View the Oregon building safety overview

Get notified when Electrical Permits in Clackamas County, OR changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.