Key Facts

Permit required
Before any electrical system work
Code adopted
California Electrical Code, current edition
Enforcement
Stop-work order, utility disconnection
Scope
Unincorporated Madera County only

Summary

Unincorporated Madera County requires a written construction permit from the building official before any electrical system is erected, altered, or installed, under the county's adopted California Electrical Code.

City-specific rules exist: Madera has its own electrical permits rules that differ from Madera County's county-level regulations. If you live in Madera, check the city-specific page instead.

(a)Except as exempted in paragraph (b) or (c) of this subsection, a written construction permit shall be obtained from the enforcing agency prior to the erection, construction, reconstruction, installation, movement, or alteration of any electrical system. Madera County shall not issue electrical permits for work in, on, or under, unpermitted structures. For electrical work to be installed in, on, or under, existing structures building permits must be obtained, inspections completed and passed prior to the issuance of any other permits.

(Ord. No. 702, § 6, 12-13-22)

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 52).

Full Breakdown

Madera County adopts the California Electrical Code under Madera County Code § 14.04.030(E) and amends it locally in Chapter 14.24. Section 14.24.120 requires a written construction permit from the enforcing agency before erecting, constructing, reconstructing, installing, moving, or altering any electrical system in the unincorporated county, with limited exceptions. The county will not issue an electrical permit for work in, on, or under a structure that itself lacks a building permit: existing structures must be permitted and pass inspection first. This governs unincorporated Madera County only; the cities of Madera and Chowchilla issue their own permits.

Violations & Fines

Electrical work done without a permit can draw a written stop-work order under § 14.24.090, and the building official may direct the serving utility to disconnect power until the work is permitted and inspected.

Frequently Asked Questions

Does Madera County require a permit for electrical work?
Yes. Madera County Code § 14.24.120 requires a written construction permit before any electrical system is erected, installed, or altered in the unincorporated county.
Can I get an electrical permit for an unpermitted structure?
No: the county will not issue an electrical permit for work in or under a structure that lacks its own building permit.

Sources & Official References

Other rules in Madera County

All Madera County rules

California rules heatmap·Compare Madera County to another location·View the California building safety overview

Get notified when Electrical Permits in Madera County, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Electrical Permits in Cities Across Madera County