Key Facts
- Code adopted
- National Electrical Code, NFPA No. 70
- Permit required
- Before installing, altering, or adding wiring
- Contractor requirement
- State-licensed electrical contractor, homeowner exception
- Jurisdiction reach
- Unincorporated area plus 1-mile ETJ zones
- Enforcing officer
- County electrical inspector
Summary
Sec. 11-123 adopts the National Electrical Code, NFPA 70, as the minimum standard for all wiring, devices, and equipment installed in the county, and Sec. 11-151 requires anyone installing, altering, or adding to electrical wiring or equipment to first secure a permit from the county electrical inspector.
The National Electrical Code, standard of the National Board of Fire Underwriters, as recommended by the National Fire Protection Association, and approved by the American Standards Association, being NFPA No. 70, is adopted as the minimum standard for the installation of all electrical wiring, devices and equipment in the county, except as otherwise specifically provided in this article; and the code is made a part of this article as fully and to the same extent as if copied in this article in full. ... Except as provided in section 11-152, any person desiring to install any electric wiring, devices, appliances or equipment within or on any building, structure or premises in the county or desiring to make any alteration in or addition to any existing electrical wiring, devices, appliances or equipment within or on any such building, structure or premises shall secure a permit from the electrical inspector.
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 15 Update 1).
Full Breakdown
Article IV of Chapter 11 governs electrical work in the unincorporated county. Sec. 11-122 requires every electrical installation to conform to state wiring law and this article, and Sec. 11-123 adopts the National Electrical Code, NFPA No. 70, as the minimum standard for all electrical wiring, devices, and equipment in the county, incorporated by reference as fully as if copied into the article. Sec. 11-151 requires anyone installing electric wiring, devices, appliances, or equipment, or altering or adding to existing wiring, to first secure a permit from the electrical inspector.
Sec. 11-152 exempts only minor repair work, such as replacing lamps or plugging portable devices into existing receptacles, and installations made by a public service corporation for generating, transmitting, or metering electricity. Sec. 11-153 restricts issuance of any permit, other than an annual permit or a homeowner's permit, to a holder of a license from the state board of examiners of electrical contractors. Under Sec. 11-154, a homeowner may obtain a permit to wire his own property, other than rental, sale, or gift property, if the electrical inspector is satisfied he can do the work safely and competently; that permit is personal to the applicant and expires automatically once the work is done.
Fee schedules are adopted by the board of commissioners and filed with the clerk to the board (Sec. 11-156), and fees are due in advance of permit issuance except for annual-permit inspections, which are paid at the time of inspection (Sec. 11-157). Sec. 11-130 extends the article's reach to the county outside any municipality's corporate limits, plus one mile beyond the limits of any municipality exercising one-mile extraterritorial jurisdiction. Roughing-in work is not considered complete under Sec. 11-132 until every joint is properly made, soldered, and taped and all switches, panels, and grounding connections are finished.
Violations & Fines
Electrical work performed without the required permit, or by an unlicensed contractor where a license is required, is enforced under the county's general penalty at Sec. 1-6, a misdemeanor punishable under G.S. 14-4 with each day a separate offense. Sec. 11-185 lets the electrical inspector disconnect service to dangerous wiring until it is made safe, and Sec. 11-187 makes it a misdemeanor to leave an unsafe pole or tower unremoved five days after the inspector's written notice.
Frequently Asked Questions
Do I need a permit for minor electrical repairs?
Can I wire my own house in New Hanover County?
What electrical code does the county enforce?
Sources & Official References
Other rules in New Hanover County
Compare New Hanover County to another location·View the North Carolina building safety overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.