Key Facts
- Governing section
- § 151.030
- Required stages
- Foundation, framing, insulation, electrical, fireproofing, final
- Who must call it in
- Permit holder or agent
- Concealed work rule
- Must be uncovered again if inspected too early
- Street-line survey
- Required before building on a public-way line
Summary
Harnett County's Inspections Department requires every permit holder to call for approval at six defined construction stages under County Code § 151.030: foundation, framing, insulation, electrical, fireproofing and final. No work may proceed past a stage until the appropriate Inspector signs off.
All holders of permits, or their agents, shall notify the Inspections Department and the appropriate Inspector at each of the following stages of construction so that approval may be given before work is continued: (a) Foundation inspection. To be made after trenches are excavated and the necessary reinforcements and forms are in place, and before concrete is placed. Drilled footings, piles, and similar types of foundations shall be inspected as installed; (b) Framing inspection. To be made after all structural framing is in place and all rough-in of plumbing and electrical, heating, and cooling systems have been installed, after all fire blocking, chimney bracing and vents are installed, but before any of the structure is enclosed or covered. ... (f) Final inspection. To be made after building or structure has all doors hung, fixtures set, and ready for occupancy, but before the building is occupied.
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: 2025 S-7: Supplement contains: Local legislation current through 11-18-2024; and State Legislation current through 2024 Legislative Service #2).
Full Breakdown
030 lays out the sequence permit holders and their agents must follow. Foundation inspection happens after trenches are excavated and forms are set, but before concrete is poured; drilled footings and piles are inspected as installed. Framing inspection comes after all structural framing and rough-in plumbing, electrical, heating and cooling are in place and fire blocking, chimney bracing and vents are installed, but before the structure is enclosed. Poured concrete structural elements are inspected before each pour. Insulation inspection happens before sheet rock or paneling is hung; electrical inspection happens before insulation goes in.
Fireproofing inspection occurs after lathing but before plastering. Final inspection happens after doors are hung and fixtures set, before occupancy, and separately before plumbing, heating, cooling or electrical equipment is put into service. Requests for inspection go to the Inspections Department office or the specific Inspector, who inspects as soon as practicable once the work is actually ready. Concealed work must be uncovered again at the Inspector's request if it was covered before approval. 030(C) also requires anyone building on a street, alley or public-place line to secure a survey of that line before construction proceeds, and makes it the Building Inspector's job to confirm no encroachment.
If an Inspector finds non-compliance at any stage, the permit holder must be notified in writing to correct it, and no additional permits are issued to that party until the correction is made or a timeline is worked out with the Inspector.
Violations & Fines
Failing to call for a required inspection, or proceeding to the next stage without the Inspector's approval, is a violation of Chapter 151 punishable under § 151.999. Ignoring a written correction order from the Inspector is likewise a chapter violation, and the Inspections Department will withhold further permits from that permit holder until the defect is fixed or a correction schedule is agreed.
Frequently Asked Questions
How many inspections does Harnett County require during a build?
Who is responsible for calling in each inspection?
What happens if work is covered up before it is inspected?
Sources & Official References
Other rules in Harnett County
Compare Harnett County to another location·View the North Carolina building safety overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.