Skip to main content
CityRuleLookup

St. Clair County, IL Building Safety: Building Inspections (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Baseline duty
Keep work open for inspection (Sec. 7-1-58)
Ten checkpoints
Footing to final inspection (Sec. 7-1-60(A)-(J))
Notice duty
Permit holder requests each inspection (7-1-62)
No concealment
Until building official approves (Sec. 7-1-63)
Occupancy
Certificate required before use (Sec. 7-1-64)
Violation
Petty offense, 730 ILCS 5/5-4.5-75

Summary

Work covered by a St. Clair County building permit must stay open for inspection at each stage under Building Regulations Sec. 7-1-58, and the building official runs through ten required checkpoints from footing and foundation to the final inspection, listed at Sec. 7-1-60(A) through (J), before the permitted work is considered complete.

These county ordinances apply to unincorporated areas of St. Clair County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

7-1-58 General. Construction or work for which a permit is required shall be subject to inspection by the building official and such construction or work shall remain accessible and exposed for inspection purposes until approved. It shall be the duty of the permit applicant to cause the work to remain accessible and exposed for inspection purposes. 7-1-60 Required inspections. The building official, upon notification, shall make the inspections set forth in Sections 7-1-60(A) through (J). A. Footing and foundation inspection. Footing and foundation inspections shall be made after excavations for footings are complete and any required reinforcing steel is in place. D. Frame inspection. Framing inspections shall be made after the roof deck or sheathing, all framing, fire blocking and bracing are in place and pipes, chimneys and vents to be concealed are complete and the rough electrical, plumbing, heating wires, pipes and ducts are approved. J. Final inspection. The final inspection shall be made after all work required by the building permit is completed.

Full Breakdown

Sec. 7-1-58 sets the baseline rule: permitted work "shall remain accessible and exposed for inspection purposes until approved," and it is the permit holder's job, not the building official's, to keep the site open and to cover any cost of removing or replacing material needed to allow the inspection. Sec. 7-1-60 lists the ten checkpoints the building official must run through on notification: footing and foundation, after excavation and reinforcing steel are placed but before concrete is poured; concrete slab and under-floor, after in-slab reinforcing and utility rough-in but before the slab or subfloor goes down; lowest floor elevation certification in flood hazard areas; framing, once the roof deck, all framing, fire blocking and bracing are up and rough electrical, plumbing and HVAC are approved; lath and gypsum board, before any plastering or joint taping; fire- and smoke-resistant penetrations, before they are concealed; energy efficiency, covering insulation R-values, fenestration U-values, duct R-values and HVAC and water-heating efficiency; any other inspection the building official deems necessary; special inspections under Chapter 17; and the final inspection, made only after all permitted work is complete.

Sec. 7-1-62 puts the burden on the permit holder to notify the building official when work is ready, and Sec. 7-1-63 bars covering or concealing any portion that fails an inspection until the building official authorizes it. A certificate of occupancy cannot issue under Sec. 7-1-64 until the building official finds no code violations at the final inspection, though work exempted from a permit under Sec. 7-1-28 never needs one.

Violations & Fines

Concealing work before it passes inspection, or occupying a building before the required certificate of occupancy issues, is enforced the same way as building without a permit: a Sec. 7-1-80 notice of violation ordering the condition corrected, escalating to legal action under Sec. 7-1-81 if ignored, and a petty-offense charge under Sec. 7-1-82 with "all fines, penalties, and sentencing" available under the Unified Code of Corrections (730 ILCS 5/5-4.5-75) for any provision of the Building Regulations violated, including the inspection and occupancy requirements.

Frequently Asked Questions

Who has to schedule building inspections, the contractor or the county?
The permit holder. Sec. 7-1-62 makes it the duty of the building permit holder or their agent to notify the building official when work is ready for each inspection stage and to provide access for it; the county does not track the schedule on its own.
How many inspections does a typical building project go through?
Sec. 7-1-60 lists ten required checkpoints: footing and foundation, concrete slab and under-floor, lowest floor elevation in flood areas, framing, lath and gypsum board, fire- and smoke-resistant penetrations, energy efficiency, any other inspection the building official requires, special inspections, and the final inspection.
Can I cover up framing or plumbing before the inspector signs off?
No. Sec. 7-1-63 requires the building official's approval at each stage before the next step of work can cover or conceal it; anything that fails must be corrected and stays exposed until the building official authorizes covering it.

Sources & Official References

Other rules in St. Clair County

All St. Clair County rules

Compare St. Clair County to another location·View the Illinois building safety overview

Get notified when Building Inspections in St. Clair County, IL changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.