Will County, IL Building Safety: Building Inspections (2026)
Key Facts
- Advance notice required
- 48 hours
- Inspection line
- 815-727-8634
- Listed inspection types
- 20 stages, footing to final
- Applies to
- unincorporated Will County only
Summary
Will County requires up to 20 staged inspections during construction, from footing to final, called 48 hours ahead of the Building Division.
Required inspections and notice for inspection. The following listed inspections are required to be made when applicable to the permitted project. The owner or contractor shall request the designated inspection 48 hours in advance. (Phone 815-727-8634) Safe access (ladder or temporary stairs) shall be provided as per OSHA rules and regulations. If someone needs to be present for the inspection it must be an individual over the age of 18. Approved plans shall be on site for inspections. Progression of inspections - work shall not be done on any part of the building or structure beyond the point indicated in each successive inspection without first obtaining the written approval of the Building Official. Such written approval shall be given only after an inspection has been made of each successive step in the construction as indicated by each of the inspections required above. This approval shall take the form of the inspector's sticker posted and signed on the premises.
(1) Footing before pour—inspection of the footings and/or isolated column footings shall be made after excavation with forms erected and required reinforcing steel in place (prior to placement of concrete). See cold weather pouring requirements in this ordinance.
(2) Slabs (interior slab below grade and interior slab at grade before pour)—concrete slab inspection for all residential, commercial, industrial and multifamily structures and their accessory structures; garage and basement
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: 2025 S-25: Supplement contains: Local legislation current through Ordinance No. 24-100, passed 4-18-2024 and Res. 23-387, passed 11-16-2023; and State legislation approved through 2024 Pamphlet #2).
Full Breakdown
In unincorporated Will County, the Building Official requires a sequence of inspections tied to construction progress: footing before pour, slabs, foundations/piers, backfill, rough building, drainage plane, final grade, and final building/electrical/mechanical/plumbing, among others. Work cannot proceed past each stage without the inspector's written approval, shown as a signed sticker posted on site. Inspections must be requested 48 hours in advance by phone, and a person 18 or older must be present with approved plans on site. Joliet, Bolingbrook, Romeoville, Plainfield and Lockport run their own building departments and are not covered by this county process.
Violations & Fines
Building beyond an uninspected stage without written approval violates § 150.009(I); the Building Official can issue a stop-work order and the permit may be revoked under § 150.009(G)(6).
Frequently Asked Questions
How far ahead must I schedule a Will County building inspection?
Can work continue before an inspection is approved?
Does this apply inside Joliet or Bolingbrook?
Sources & Official References
Other rules in Will County
Compare Will County to another location·View the Illinois building safety overview