Key Facts

Governing section
Clackamas County Code § 9.02.310
Duty holder
Permit holder, not the county
Permit expiration
180 days without an approved inspection
Renewal fee after lapse
Half fee (6-12 mo.), full fee (12 mo.+)
Related section
Code § 9.02.270 automatic expiration rules

Summary

Clackamas County puts the duty to schedule inspections on the permit holder, not the county: the permittee must request every required inspection, give inspectors site access, and keep the work exposed until it's approved. Skipping inspections doesn't just risk a stop-work order, it automatically expires the building permit.

These county ordinances apply to unincorporated areas of Clackamas County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

It shall be the duty of the permit holder or their agent to request all necessary inspections in a timely manner and according to the policies of Clackamas County, provide access to the site, and provide all necessary equipment to make inspections as determined by the building official. The permit holder shall not proceed with construction until authorized by the building official. It shall be the duty of the permit holder to cause the work to remain accessible and exposed for inspection purposes. Any expense incurred by the permit holder to remove or replace any material required for proper inspection shall be the responsibility of the permit holder or their agent. Failure to request inspections shall result in expiration of the permit as per Section 9.02.270. The county has no obligation, responsibility, or liability to follow up on permits for which necessary inspections have not been requested or which are at risk of expiration under Section 9.02.270. The permittee shall bear all such responsibility and liability.

Full Breakdown

' The permit holder cannot proceed with construction until the Building Official authorizes it, and must keep completed work 'accessible and exposed for inspection purposes,' meaning framing or utility runs may need to stay uncovered until sign-off. 270: the permit automatically expires if the work goes 180 days without an approved inspection, the same 180-day clock that applies if work is never commenced or is abandoned. The chapter states the county 'has no obligation, responsibility, or liability to follow up on permits for which necessary inspections have not been requested,' putting that risk on the permittee.

080 subjects any building within the dangerous-buildings chapter, and any work requiring a permit, to inspection by the Building Official. Inspection authority under both chapters rests with the Building Official and designated deputies, including the Deputy Building Codes Administrator and the Structural/Mechanical Inspector Supervisor.

Violations & Fines

Failing to call for inspections lets the permit lapse under Section 9.02.270, forcing the owner to renew it; if the lapse runs six months to a year the county charges half the original permit fee, or the full fee again past a year, plus hourly plan-review charges. Proceeding with construction the Building Official has not authorized, or covering work before it is inspected, is enforceable under Section 9.02.330 through injunction, abatement or other court action, and Section 9.02.280 adds an investigation fee for work started without a permit, whether or not a permit is ultimately issued.

Frequently Asked Questions

Who is responsible for scheduling building inspections in Clackamas County?
Section 9.02.310 places that duty on the permit holder or their agent, not the county. The permittee must request each required inspection in a timely manner, give inspectors site access, and keep the completed work accessible and exposed until the Building Official signs off. The county states it has no obligation to follow up on unrequested inspections.
What happens if I don't schedule an inspection in time?
Under Section 9.02.310, failing to request inspections causes the permit to expire under Section 9.02.270's 180-day rule, the same clock used for work that is never started or is abandoned. Once expired, resuming work requires renewing the permit, and depending on how long it sat idle you may owe half or the full original permit fee again.
Can I cover up work before the inspector sees it?
No. Section 9.02.310 requires the permit holder to keep the work 'accessible and exposed for inspection purposes,' and construction cannot proceed past an inspection point until the Building Official authorizes it. Any cost to remove or replace material covered too early to allow inspection falls on the permit holder or their agent.
Who has authority to inspect a Clackamas County building?
The Building Official and authorized representatives, including the Deputy Building Codes Administrator and the Structural/Mechanical Inspector Supervisor, hold inspection authority under Sections 9.01.080 and 9.02.310. Where fire code issues arise, the Building Official must consult a fire marshal before acting under the dangerous-buildings chapter.

Sources & Official References

Other rules in Clackamas County

All Clackamas County rules

Compare Clackamas County to another location·View the Oregon building safety overview

Get notified when Building Inspections in Clackamas County, OR changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.