Bernalillo County, NM Building Safety: Building Inspections (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Who requests it
The permit holder, not the county
Notice required
At least 1 working day
Inspection stages
16 listed, foundation to final
Enforcing office
Bernalillo County Building Department
Applies to
Unincorporated county only

Summary

Permit holders in unincorporated Bernalillo County must request each construction inspection from the County Building Department, giving the address, permit number, and inspection type, at least one working day ahead.

These county ordinances apply to unincorporated areas of Bernalillo County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

110.1.3 Inspections Requests. It shall be the duty of the permit holder doing the work authorized by a permit to notify the Bernalillo County Building Department that such work is ready for inspection. Notification shall include at least the following: correct street address, suite number and/or building number, type of inspection, permit holder's name, permit number and/or sub-permit number. The CBO may require that every request for inspection be filed at least one working day before such inspection is desired.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 92).

Full Breakdown

Bernalillo County adopted the International Building and Residential Codes with local amendments, printed as the Uniform Administrative Code in Exhibit A to Code Sec. 10-36. Under Section 110.1.3, the permit holder, not the county, must notify the Building Department when work is ready for inspection, supplying the street address, permit or sub-permit number, inspection type, and permit holder's name. The Code Building Official (CBO) can require at least one working day's notice. Section 110.5 then lists 16 required building-inspection stages, from foundation through final, plus separate lists for electrical, mechanical, and solar work. This applies only to unincorporated county land; Albuquerque runs its own inspection process under its Integrated Development Ordinance.

Violations & Fines

Skipping a required inspection or failing to keep work exposed for inspection is a Code violation punishable, under Sec. 1-6, by a fine up to $300, up to 90 days in jail, or both, on top of any permit or occupancy delay.

Frequently Asked Questions

Who has to schedule the inspection, me or the county?
You, the permit holder. Sec. 110.1.3 makes it your duty to notify the Building Department that the work is ready, with the address and permit number.
Does this apply if I live in Albuquerque?
No. This Code governs unincorporated Bernalillo County only; Albuquerque enforces inspections under its own Integrated Development Ordinance.
How much notice does the county need before an inspection?
The CBO may require the inspection request be filed at least one working day before the inspection is desired, per Sec. 110.1.3.

Sources & Official References

Other rules in Bernalillo County

All Bernalillo County rules

Compare Bernalillo County to another location·View the New Mexico building safety overview

Get notified when Building Inspections in Bernalillo County, NM changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Building Inspections in Cities Across Bernalillo County