St. Clair County, IL Building Safety: Building Inspections (2026)
Key Facts
- Baseline duty
- Keep work open for inspection (Sec. 7-1-58)
- Ten checkpoints
- Footing to final inspection (Sec. 7-1-60(A)-(J))
- Notice duty
- Permit holder requests each inspection (7-1-62)
- No concealment
- Until building official approves (Sec. 7-1-63)
- Occupancy
- Certificate required before use (Sec. 7-1-64)
- Violation
- Petty offense, 730 ILCS 5/5-4.5-75
Summary
Work covered by a St. Clair County building permit must stay open for inspection at each stage under Building Regulations Sec. 7-1-58, and the building official runs through ten required checkpoints from footing and foundation to the final inspection, listed at Sec. 7-1-60(A) through (J), before the permitted work is considered complete.
7-1-58 General. Construction or work for which a permit is required shall be subject to inspection by the building official and such construction or work shall remain accessible and exposed for inspection purposes until approved. It shall be the duty of the permit applicant to cause the work to remain accessible and exposed for inspection purposes. 7-1-60 Required inspections. The building official, upon notification, shall make the inspections set forth in Sections 7-1-60(A) through (J). A. Footing and foundation inspection. Footing and foundation inspections shall be made after excavations for footings are complete and any required reinforcing steel is in place. D. Frame inspection. Framing inspections shall be made after the roof deck or sheathing, all framing, fire blocking and bracing are in place and pipes, chimneys and vents to be concealed are complete and the rough electrical, plumbing, heating wires, pipes and ducts are approved. J. Final inspection. The final inspection shall be made after all work required by the building permit is completed.
Full Breakdown
Sec. 7-1-58 sets the baseline rule: permitted work "shall remain accessible and exposed for inspection purposes until approved," and it is the permit holder's job, not the building official's, to keep the site open and to cover any cost of removing or replacing material needed to allow the inspection. Sec. 7-1-60 lists the ten checkpoints the building official must run through on notification: footing and foundation, after excavation and reinforcing steel are placed but before concrete is poured; concrete slab and under-floor, after in-slab reinforcing and utility rough-in but before the slab or subfloor goes down; lowest floor elevation certification in flood hazard areas; framing, once the roof deck, all framing, fire blocking and bracing are up and rough electrical, plumbing and HVAC are approved; lath and gypsum board, before any plastering or joint taping; fire- and smoke-resistant penetrations, before they are concealed; energy efficiency, covering insulation R-values, fenestration U-values, duct R-values and HVAC and water-heating efficiency; any other inspection the building official deems necessary; special inspections under Chapter 17; and the final inspection, made only after all permitted work is complete.
Sec. 7-1-62 puts the burden on the permit holder to notify the building official when work is ready, and Sec. 7-1-63 bars covering or concealing any portion that fails an inspection until the building official authorizes it. A certificate of occupancy cannot issue under Sec. 7-1-64 until the building official finds no code violations at the final inspection, though work exempted from a permit under Sec. 7-1-28 never needs one.
Violations & Fines
Concealing work before it passes inspection, or occupying a building before the required certificate of occupancy issues, is enforced the same way as building without a permit: a Sec. 7-1-80 notice of violation ordering the condition corrected, escalating to legal action under Sec. 7-1-81 if ignored, and a petty-offense charge under Sec. 7-1-82 with "all fines, penalties, and sentencing" available under the Unified Code of Corrections (730 ILCS 5/5-4.5-75) for any provision of the Building Regulations violated, including the inspection and occupancy requirements.
Frequently Asked Questions
Who has to schedule building inspections, the contractor or the county?
How many inspections does a typical building project go through?
Can I cover up framing or plumbing before the inspector signs off?
Sources & Official References
Other rules in St. Clair County