Collier County, FL Building Safety: Building Inspections (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Governing law
Collier County Code Sec. 22-26 (FBC 107.3.1, 110.3)
Plan stamp
'Reviewed for Code Compliance'
Foundation inspection
after trenches excavated, forms erected
Spot survey deadline
10 calendar days after inspection
Surveyor
Florida-registered land surveyor required
Max penalty
$500 fine or 60 days jail

Summary

Collier County stamps every approved building permit set 'Reviewed for Code Compliance' under Sec. 107.3.1 and keeps one set on file while the other stays on-site for the inspector, and Sec. 110.3 requires a foundation inspection after trenches are excavated and forms erected, followed by a licensed surveyor's spot survey within ten calendar days confirming the building's location and floor elevation.

These county ordinances apply to unincorporated areas of Collier County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

107.3.1 Approval of construction documents. The following amendment to the administrative provisions of the Florida Building Code has been established for Collier County based on Section 107.3 of the Florida Building Code and Section 553.74(4)(a), Florida Statutes. When the building official issues a permit, the construction documents shall be approved, in writing or by stamp, as "Reviewed for Code Compliance." One set of construction documents so reviewed shall be retained by the building official. The other set shall be returned to the applicant, shall be kept at the site of work, and shall be open to inspection by the building official or a duly authorized representative. Digital copies available at the site of work and open to inspection by the building official or a duly authorized representative will also be accepted. 110.3 Required Inspections. Building 1.Foundation inspection. To be made after trenches are excavated and forms erected and shall at a minimum include the following building components:1.2The permit holder shall submit, within 10 calendar days of this inspection, a spot survey depicting the building foundation to the authority having jurisdiction.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 126 | Land Development Code: Supplement 33).

Full Breakdown

Once the building official approves construction documents, Sec. 1 requires the set to be marked, in writing or by stamp, "Reviewed for Code Compliance"; the county keeps one reviewed set, and the other must stay at the job site, open to inspection by the building official or an authorized representative, though a digital copy on-site now satisfies that requirement too. Sec. 3 sets out the foundation inspection: it has to occur after trenches are excavated and forms erected, and within ten calendar days of that inspection the permit holder must submit a spot survey depicting the building's foundation to the authority having jurisdiction.

Where a structure doesn't get a foundation inspection but needs a minimum floor elevation, the spot survey instead becomes due before the certificate of occupancy or completion is issued. That survey has to be prepared and certified by a Florida-registered land surveyor in a form the building official accepts, though the building official can waive the requirement for certain small, non-habitable structures. The county's definitions section, also part of Sec. 22-26, distinguishes a "repair" (restoring or renewing a damaged part) from a "replacement" (removing an entire component and installing a new one) and from "like for like" work (similar use, type, operation and connection), distinctions that determine which permit exemptions and inspection triggers apply to a given repair job.

Violations & Fines

Skipping a required inspection or proceeding past the foundation stage without the surveyor's spot survey is enforced under Sec. 22-28 like any other building-code violation: a fine of up to $500, up to sixty days in the county jail, or both, with each day of continued noncompliance treated as a separate offense, court costs added, and further enforcement available under F.S. Section 125.69 or Chapter 162.

Frequently Asked Questions

What is a spot survey and when is it due in Collier County?
It's a Florida-registered land surveyor's certified drawing of the building's foundation location and elevation. Sec. 110.3 requires it within ten calendar days of the foundation inspection, or before the certificate of occupancy if the structure has no foundation inspection but needs a minimum floor elevation, unless the building official waives it for a small, non-habitable structure.
Do I need to keep my approved plans on the job site?
Yes. Sec. 107.3.1 requires the building official to stamp approved plans 'Reviewed for Code Compliance,' keep one set on file, and return the other to be kept at the site of work where the building official or an authorized representative can inspect it; a digital copy available on-site now satisfies that same requirement.
What's the difference between a repair and a replacement under Collier's building code?
Collier's definitions treat a 'repair' as restoring or renewing a damaged part, a 'replacement' as removing an entire component and installing a new one, and 'like for like' as matching use, type, operation and connection. Which label applies decides whether a job qualifies for a Sec. 105.2.4 exemption or instead triggers the foundation inspection and spot-survey steps under Sec. 110.3.

Sources & Official References

Other rules in Collier County

All Collier County rules

Florida rules heatmap·Compare Collier County to another location·View the Florida building safety overview

Get notified when Building Inspections in Collier County, FL changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.