Key Facts

Adopted code
International Plumbing Code, State of Utah amended
Local amendment
Sections 305.6.1 & 904.1: 12-inch cover depth
Amending ordinance
Ordinance 2015-1049-O, April 21, 2015
Governing section
County Code § 9-1-4
Default penalty
Class B misdemeanor, up to $1,000 fine

Summary

Washington County adopts the International Plumbing Code, as amended by the State of Utah, under County Code section 9-1-4, and locally amends two sections governing pipe cover depth. Plumbing work in the unincorporated county needs a permit from the county building inspector before installation begins.

City-specific rules exist: St. George has its own plumbing permits rules that differ from Washington County's county-level regulations. If you live in St. George, check the city-specific page instead.

The most recent version adopted by the State of Utah of the following codes and the appendices and the State's amendment are incorporated by reference and adopted as the Building Codes of Washington County: ... International Plumbing Code, National Electrical Code, HUD Code, and the Model Manufactured Home Installation Standard ... B. The cited sections of the international plumbing code are amended as follows: Section 305.6.1. Insert: 12 inches (304 mm) Section 904.1. Insert: 12 inches (304 mm) (Ord. 2015-1049-O, 4-21-2015)

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: 2026 S-17: Code current through: Ord. 2026-1329-O, passed 8-18-2026).

Full Breakdown

Section 9-1-4 adopts the International Plumbing Code, alongside the National Electrical Code and the other International Codes, as part of the county's Building Codes, with three copies kept on file at the Washington County Clerk's office. 1 is amended the same way, both adopted by Ordinance 2015-1049-O on April 21, 2015. As with all building codes adopted under this chapter, no permit for plumbing work can be issued under section 9-1-7 unless the installation meets the adopted, locally amended International Plumbing Code as well as the zoning, subdivision and groundwater protection ordinances.

Permit, plan review and investigation fees follow the fee table the county commission adopts under section 9-1-8, and no certificate of occupancy issues under section 9-1-9 until the plumbing passes inspection. The county building inspector administers the chapter under section 9-1-10, and section 9-1-11 bars that office from imposing any plumbing standard beyond what the adopted code specifies. Anyone who disagrees with how a plumbing provision was applied can appeal to the board of building appeals under sections 9-1-12 and 9-1-13.

Violations & Fines

Installing or altering plumbing without a permit, or work that departs from the adopted and locally amended International Plumbing Code, violates section 9-1-5's ban on construction or repair that does not comply with the adopted codes. Chapter 1 of Title 9 carries no separate fine, so the general penalty in section 1-4-1 applies: up to a $1,000.00 fine and up to six months in jail as a class B misdemeanor.

Frequently Asked Questions

What plumbing code does Washington County enforce?
Section 9-1-4 adopts the International Plumbing Code as most recently amended by the State of Utah, and locally amends Sections 305.6.1 and 904.1 to require a minimum 12-inch (304 mm) pipe cover, adopted by Ordinance 2015-1049-O on April 21, 2015 to fit local soil conditions.
Is a permit required before plumbing work starts in the unincorporated county?
Yes. Section 9-1-7 blocks issuance of any building permit, plumbing included, unless the work meets the adopted International Plumbing Code plus the county's zoning, subdivision and groundwater protection ordinances. The county building inspector reviews and approves plans first.
What is the minimum pipe cover depth under the local plumbing amendment?
Twelve inches (304 mm). The county amended IPC Sections 305.6.1 and 904.1 to insert that minimum cover requirement rather than adopting the model code's default depth, a change the county commission made by Ordinance 2015-1049-O in 2015.

Sources & Official References

Other rules in Washington County

All Washington County rules

Compare Washington County to another location·View the Utah building safety overview

Get notified when Plumbing Permits in Washington County, UT changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Plumbing Permits in Cities Across Washington County