Key Facts

Code adopted
2025 California Plumbing Code, Title 24 Pt. 5
Gas shutoff valve
earthquake-actuated valve required, new/replaced gas lines
Exempt work
minor leak/stoppage repairs only, SCCC § 12.10.315(B)
Water demand
Appendix M calculator adopted
Enforcing agency
Santa Cruz County Building Official

Summary

Unincorporated Santa Cruz County enforces the 2025 California Plumbing Code with local amendments requiring earthquake-actuated gas shutoff valves on new or replacement gas lines and adopting the water demand calculator appendix; permits are required for most plumbing work beyond minor repairs.

These county ordinances apply to unincorporated areas of Santa Cruz County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

§ 12.10.235. 2025 California Plumbing Code adopted. The Plumbing Code for the County of Santa Cruz shall be the latest printing of the 2025 Edition of the California Plumbing Code... (B) Shutoff Valves Amendment. Section 1208.14 of the 2025 California Plumbing Code is hereby amended by adding Section 1208.14.1 to read: Section 1208.14.1 Earthquake-actuated gas shutoff valves. New gas piping systems, replacement gas piping systems, and new or replacement gas meter installations, shall have a listed and approved earthquake-actuated gas shutoff valve (sized for the BTU demand of the system) installed just prior to the meter connection or connection to a propane tank, prior to the release of utilities.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: rev 5004302; v11 updated 2026-05-19; through 05-19-2026).

Full Breakdown

235 adopts the latest printing of the 2025 California Plumbing Code (Part 5, Title 24 of the California Code of Regulations) as the county's plumbing code, with three local amendments. 315(B), which limits no-permit plumbing work to stopping small leaks and clearing stoppages, provided the repair does not require replacing or rearranging pipes, valves, or fixtures. 1 requires every new gas piping system, replacement gas piping system, and new or replacement gas meter installation to have a listed, approved earthquake-actuated gas shutoff valve, sized for the system's full BTU demand, installed immediately before the meter or propane tank connection and before utilities are released.

Third, Appendix M of the 2025 Plumbing Code, the water demand calculator, is formally adopted for sizing water supply piping. 315 exemption list. 1 flow standard even though the swap itself is permit-exempt.

Violations & Fines

Plumbing work performed without the required permit, or a gas line or meter installation completed without the mandated earthquake-actuated shutoff valve, is subject to enforcement by the Building Official under the general permit-compliance provisions of Chapter 12.10; unpermitted work can be red-tagged and requires retroactive permitting and inspection before use or occupancy is approved.

Frequently Asked Questions

Do I need a permit to fix a leaking pipe in my Santa Cruz County home?
Not for stopping a simple leak in a drain, waste, or vent line, per SCCC § 12.10.315(B). But if the trap, drainpipe, or vent pipe is defective and must be removed and replaced, that becomes new work requiring a permit and inspection under the same section.
What is the earthquake shutoff valve rule for gas lines?
SCCC § 12.10.235(B) requires a listed, approved earthquake-actuated gas shutoff valve, sized for the full BTU demand of the gas system, on every new gas piping system, replacement gas piping system, and new or replacement gas meter installation, installed just before the meter or propane tank connection.
Which plumbing code edition applies to unincorporated Santa Cruz County?
The county has adopted the 2025 California Plumbing Code, Part 5 of Title 24, under SCCC § 12.10.235, with local amendments covering exempt work, earthquake shutoff valves, and the Appendix M water demand calculator for sizing supply piping.

Sources & Official References

Other rules in Santa Cruz County

All Santa Cruz County rules

California rules heatmap·Compare Santa Cruz County to another location·View the California building safety overview

Get notified when Plumbing Permits in Santa Cruz County, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Plumbing Permits in Cities Across Santa Cruz County