Madera County, CA Building Setbacks & Zoning: Lot Coverage Limits (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

RX / RUM zones
85% max lot coverage
RUS / RT zones
80% max lot coverage
RRS-1ac / RRM / RM
40% max lot coverage
RRS-2/2.5/3, RRS-5, RRS-10
20% max lot coverage
RMS zone
no numeric coverage cap listed
Violation
misdemeanor, per-day offense
Variance appeal window
15 days after hearing

Summary

Unincorporated Madera County caps the share of a residential lot that structures may cover through the development standards table in Chapter 18.11. The limit is set separately for each residential zone, running from 20 percent in the RRS-2 through RRS-10 rural zones up to 85 percent in the urban RX and RUM zones, with no numeric cap listed for the RMS mountain zone.

City-specific rules exist: Madera has its own lot coverage limits rules that differ from Madera County's county-level regulations. If you live in Madera, check the city-specific page instead.

The development standards table for residential zones identifies the parcel size, density standards, lot coverage, setbacks and height regulations that apply in the residential zones. ... Max. lot coverage (%) 80 85 40 20 20 20 • 80 85 40 40 ... Setbacks are measured from the property line to the wall of the structure. Front setbacks are measured from the road right-of-way to the wall of the structure.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 52).

Full Breakdown

lot coverage (%)' row of that table sets the following limits by zone: RUS 80%, RX 85%, RRS on one-acre minimum lots 40%, RRS-2/RRS-2½/RRS-3 20%, RRS-5 20%, RRS-10 20%, RMS (dash, no coverage percentage listed), RT 80%, RUM 85%, RRM 40%, and RM 40%. 010(B), a dash in the table 'indicates no specific regulation of that requirement,' so the RMS mountain single-family zone carries no numeric lot coverage cap even though it has minimum lot size and setback standards. These figures apply only inside unincorporated Madera County; the cities of Madera and Chowchilla set their own zoning and are not governed by this county code.

The same section ties lot coverage to the county's setback rule: 'Setbacks are measured from the property line to the wall of the structure. Front setbacks are measured from the road right-of-way to the wall of the structure,' and where a parcel fronts two roadways, a twenty-five-foot front setback applies to each. The table also carries maximum floor area ratio figures by zone and story count and a required parking count of two spaces per unit, both of which interact with how much of a lot can practically be built out.

This standard traces to Ord. No. 525VV § 3 (Exh. C), adopted July 18, 2017, and was most recently amended by Ord. No. 525YY § 2 (December 17, 2024) and Ord. No. 525ZZ § 3 (October 14, 2025).

Violations & Fines

Exceeding the lot coverage limit is enforced under Chapter 18.112. Any structure built in conflict with Title 18 'is declared to be unlawful and a public nuisance' (§ 18.112.020), and violating the title is a misdemeanor with a 'separate offense for each and every day during which any violation... is committed' (§ 18.112.010). If the zoning administrator abates the nuisance after notice, the county may recover abatement costs plus 'a penalty of ten dollars for each day the nuisance remained after service of the notice' (§ 18.112.070, § 18.112.080), and injunctive relief is available under § 18.112.085. A permit application for construction already built in violation of the title 'shall require a fee double the application fee' under § 18.112.120.

Frequently Asked Questions

What is the maximum lot coverage for a house in unincorporated Madera County?
It depends on the residential zone. Madera County Code § 18.11.120 sets the cap at 20% in the RRS-2 through RRS-10 rural single-family zones, 40% in the RRS-1 acre, RRM and RM zones, 80% in RUS and RT, and 85% in RX and RUM. Check your parcel's zone designation with the planning department before designing to a percentage.
Does the RMS mountain zone have a lot coverage limit?
No. The § 18.11.120 development standards table shows a dash under 'Max. lot coverage (%)' for the RMS zone, and § 18.10.010(B) states a dash 'indicates no specific regulation of that requirement.' RMS parcels still must meet the zone's minimum lot size, setback and height standards.
What happens if I build past the lot coverage limit without a permit?
It is treated as a public nuisance and a misdemeanor under Chapter 18.112, with a separate violation for each day it continues. The county can abate the condition at the owner's expense, recover a $10-per-day penalty after notice, seek an injunction, and charge double the normal fee on any permit application filed for work already built in violation.
Can a property owner get relief from the lot coverage limit?
Yes, through the variance process in Chapter 18.106. An applicant must show exceptional circumstances tied to the property under § 18.106.040, and structure location variances can be granted by the zoning administrator without a public hearing. Any interested party may appeal a decision within 15 days of the hearing under § 18.108.080.

Sources & Official References

Other rules in Madera County

All Madera County rules

California rules heatmap·Compare Madera County to another location·View the California building setbacks & zoning overview

Get notified when Lot Coverage Limits in Madera County, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Lot Coverage Limits in Cities Across Madera County