Significant Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified July 2026

Key Facts

Dedicated Ordinance
None; general industrial zoning
Allowed Districts
ML, MH, MG (MB coastal)
Approval
Use Permit + CEQA review
Coastal Zone
Coastal Development Permit required
Jurisdiction
Unincorporated county only

Summary

Humboldt County has no dedicated data center ordinance. In the unincorporated county a data center is an industrial use for the ML, MG, or MH districts, needing a Use Permit, CEQA review, and, in the coastal zone, a Coastal Development Permit.

These county ordinances apply to unincorporated areas of Humboldt County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

The Limited Industrial or ML Zone is intended to apply to areas in which light manufacturing and heavy commercial uses of the non-nuisance type and large administrative facilities are permitted.

Source: Humboldt County Code — Title III Div. 1 Zoning (Ch. 314 non-coastal, Ch. 313 coastal) & General Plan Ch. 13 Noise ElementView official code

Official source re-checked September 8, 2026: no newer edition of the code had been published (publisher’s edition: current through Ordinance 2788, passed May 12, 2026).

Full Breakdown

Unincorporated Humboldt County regulates data centers only through general industrial zoning, not a data-center-specific chapter. Land use runs under two regimes: County Code Chapter 314 outside the coastal zone and Chapter 313 inside it. A server or computing facility is an industrial use, sited in the Limited Industrial (ML), Heavy Industrial (MH), or Industrial General (MG) districts; the ML zone is meant for light manufacturing and large administrative facilities of the non-nuisance type. A facility of utility scale requires a discretionary Use Permit, which triggers CEQA review of water, power, traffic, and noise. Because Humboldt is a coastal county, any site inside the Coastal Zone also needs a Coastal Development Permit under the county's certified Local Coastal Program.

Violations & Fines

Building a data center outside a designated industrial zone, or without a required Use Permit, CEQA clearance, or (in the Coastal Zone) a Coastal Development Permit, is a zoning violation that can halt the project until it conforms.

Frequently Asked Questions

Where can a data center be built in unincorporated Humboldt County?
Only in an industrial zone. ML or MH outside the coastal zone, or ML, MG or MB inside it. It is an industrial use needing a Use Permit, CEQA review, and a Coastal Development Permit in the Coastal Zone.
Does the county zoning code apply inside Eureka, Arcata, or Fortuna?
No. Chapters 313 and 314 govern only the unincorporated county. Eureka, Arcata, Fortuna, and the county's other cities each adopt and enforce their own zoning codes within city limits.
Does Humboldt County have data center rules, and how can I weigh in?
There is no dedicated data-center ordinance; data centers are governed by general industrial zoning, CEQA, coastal permitting, and General Plan noise standards. To advocate for one, contact the Board of Supervisors at humboldtgov.org/167/Board-of-Supervisors.

Sources & Official References

Other rules in Humboldt County

All Humboldt County rules

California rules heatmap·Compare Humboldt County to another location·View the California data centers & crypto mining overview

Get notified when Data Center Zoning & Siting in Humboldt County, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.