San Benito County, CA Data Centers & Crypto Mining: Data Center Zoning & Siting (2026)

Significant Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Dedicated Rule
None; treated as light industrial
Industrial Zones
BP, M-1, M-2
Approval
Administrative Use Permit plus CEQA
Standards
25 ft front, 40 ft height
Jurisdiction
Unincorporated county only

Summary

San Benito County has no data-center ordinance. A data center is treated as a light industrial facility, allowed in the Business Park (BP), Light Industrial (M-1), or Heavy Industrial (M-2) district with an Administrative Use Permit under Title 25, Section 25.03.007, plus CEQA review. County zoning covers unincorporated land only.

These county ordinances apply to unincorporated areas of San Benito County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

The M-1 district is intended to allow light industrial development near existing transportation systems (e.g., highways, rail, air). This includes: warehouses, contractor yards, nurseries, lumber yards, auto repair shops, light manufacturing and/or assembly, and research and development operations that do not cause significant environmental hazards or create major pollution.

(D)   Heavy Industrial (M-2) District — Intent. The M-2 district is intended to provide areas for heavy industrial activities that are not suitable for urban areas because of their size, noise, dust, traffic, or safety concerns. This could include large-scale manufacturing operations, mining and aggregate production facilities, recycling transfer centers, chemical and explosives manufacturing, or other similar uses.

(E)   BP, M-1 and M-2 permitted uses. The table below designates uses are permitted, administratively permitted, conditionally permitted, or prohibited in BP, M-1 and M-2 districts. The regulations in this section apply to every lot and building site in the BP, M-1 and M-2 zoning districts, except where modified by a combining zone. Table 25.03-H

Land Use Regulations -Industrial Zones “P” = Permitted Use “A” = Administrative Use Permit Required “C” = Conditional Use Permit Required “—” = Not Allowed All new structures require review, per

Source: San Benito County Code, Title 25 (Zoning) & Chapter 19.39 (Noise Control Regulations)View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: 2025 S-28: current through Ordinance 1078).

Full Breakdown

There is no data-center-specific use in the county code. Under Title 25, Section 25.03.007 (Ordinance 1043, 2022), a server facility fits the "light industrial facilities" classification in Table 25.03-H, which requires an Administrative Use Permit in the BP, M-1, and M-2 districts, confirmed through the Similar Uses interpretation in Chapter 25.01. Industrial standards set a 25-foot front and street-side setback, a 40-foot height limit, and a 0.8 floor area ratio, with a 25-foot side setback where a use abuts a residential zone. A large facility with backup generators or fuel storage can trigger a Conditional Use Permit and CEQA review of power, water, and noise. This governs unincorporated land only; Hollister and San Juan Bautista set their own zoning.

Violations & Fines

Building a data center without the required Administrative or Conditional Use Permit, or in a non-industrial zone, is a zoning violation. The Resource Management Agency can withhold building permits, issue stop-work orders, and pursue code enforcement.

Frequently Asked Questions

Where can a data center be built in unincorporated San Benito County?
In an industrial district: Business Park (BP), Light Industrial (M-1), or Heavy Industrial (M-2) under Section 25.03.007. It is classified as a light industrial facility needing an Administrative Use Permit and CEQA review.
Does San Benito County have data center rules, and how can I weigh in?
No. San Benito County has no dedicated data-center ordinance; one is permitted only as a light industrial use. To advocate for tailored rules, contact the Board of Supervisors at sanbenitocountyca.gov/government/county-of-san-benito-board-of-supervisors-bos.
Do county zoning rules apply inside Hollister or San Juan Bautista?
No. Title 25 governs only unincorporated San Benito County. The cities of Hollister and San Juan Bautista each adopt and enforce their own zoning code within their limits.

Sources & Official References

Other rules in San Benito County

All San Benito County rules

California rules heatmap·Compare San Benito County to another location·View the California data centers & crypto mining overview

Get notified when Data Center Zoning & Siting in San Benito County, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.