Harris County, TX Environmental Rules: Erosion Control (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified August 2026

Key Facts

Removal deadline
30 days after stabilization/NOT
Civil penalty
Up to $1,000 per day
Correction window
72 hours after notice
Enforced by
County Engineer / County Attorney

Summary

Construction sites in unincorporated Harris County need an SWQ Permit with a site plan showing erosion control measures, and must remove temporary structural erosion controls within 30 days of final stabilization or filing a Notice of Termination.

City-specific rules exist: Tomball, Humble, Houston, Pasadena, Baytown, and La Porte have their own erosion control rules that differ from Harris County's county-level regulations. If you live in one of those cities, check the city-specific page instead.

A site operator that is required to post notice as a large or small construction site under the Texas Construction General Permit (TXR150000) shall remove all temporary structural erosion controls no later than 30 days after submittal of the NOT or after final stabilization has been achieved on all portions of the site that are the responsibility of the permittee. For large construction sites, primary and secondary operators shall have joint and several liability for compliance with this provision.

Source: Harris County SWQ RegulationsView official code

Full Breakdown

Operators seeking coverage under the Texas Construction General Permit must submit a site plan detailing erosion control measures with their NOI to the Stormwater Quality Engineer. Harris County then makes periodic unannounced inspections checking the condition and effectiveness of erosion and sediment control devices and entrance stabilization to reduce vehicle tracking. Once a large or small construction site reaches final stabilization or the operator files a Notice of Termination, all temporary structural erosion controls must be removed within 30 days. Large-site primary and secondary operators share joint and several liability for that removal; on small sites, operators and property owners share it.

Violations & Fines

County Attorney can sue for civil penalties up to $1,000 per day per violation and to enjoin the violation; each day counts separately. Uncorrected inspection deficiencies (72-hour correction window) trigger a reinspection fee on top of any penalty.

Frequently Asked Questions

Do I need a permit for erosion control on a Harris County construction site?
Yes. An SWQ Permit is required alongside your Texas Construction General Permit coverage, and your NOI must include a site plan showing erosion control measures.
How long can silt fence and other temporary erosion controls stay up after construction?
No more than 30 days after you submit your Notice of Termination or reach final stabilization on that portion of the site, whichever governs, under Sec 3.01.

Sources & Official References

Other rules in Harris County

All Harris County rules

Texas rules heatmap·Compare Harris County to another location·View the Texas environmental rules overview

Get notified when Erosion Control in Harris County, TX changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Erosion Control in Cities Across Harris County