Jefferson County, MO Environmental Rules: Erosion Control (2026)
Key Facts
- Permit threshold
- 5,000 square feet of land disturbance
- BMPs required
- At 1 acre or more disturbed
- Fee (2025)
- $250 to $2,750+ scaled by acreage
- Fee (2026)
- $300 to $3,750+ scaled by acreage
- Minimum fine
- $200 per day of violation
- Enforced by
- County Department of Public Works
Summary
Jefferson County requires a land disturbance permit before any grading, clearing or construction activity that disturbs 5,000 square feet or more of unincorporated county land. Projects of one acre or larger must install stormwater best management practices, and permit fees scale with the acreage disturbed under Chapter 505 of the county code.
Permit Required. No person may engage in any land disturbance activity, including persons engaged in land disturbance activity related to utility installation or maintenance, without first obtaining a land disturbance permit from the County, except as provided in this Chapter. All new or redevelopment projects disturbing five thousand (5,000) square feet or greater are required to obtain a land disturbance permit. Land disturbance activities that disturb five thousand (5,000) square feet to less than one (1) acre are generally not required to implement permanent water quality Best Management Practices (BMPs) unless the Director of Public Works determines that a permanent BMP such as a swale, ditch, check dam or other similar measure is necessary, or unless they are part of common plan of development or sale. Land disturbance activities of one (1) acre or more, including projects less than one (1) acre that are part of a larger common plan of development or sale, are required to install structural or non-structural Best Management Practices (BMPs) which address the quality of long-term stormwater runoff and effectively remove stormwater pollution.
Full Breakdown
190 of the county code, bars anyone, including utility crews, from beginning a land disturbance activity such as mechanized clearing or grading without a County land disturbance permit. The permit threshold is 5,000 square feet: any new or redevelopment project disturbing that much ground or more must obtain a permit from the Director of Public Works before work starts, and other construction permits for the same site are held up until it is issued. Between 5,000 square feet and one acre, the county does not usually require a permanent stormwater best management practice such as a swale, ditch or check dam unless the Director determines one is needed or the project is part of a larger common plan of development.
At one acre or more, or for smaller phases of a larger common plan, the applicant must design and install structural or non-structural BMPs that address long-term stormwater runoff quality. The permit fee is tiered by acreage: through the end of 2025 it runs from $250 for sites under an acre up to $2,750 plus $10 per acre over 25 acres for the largest sites, and a new fee schedule starting January 1, 2026 raises the base fees to $300 through $3,750 plus $10 per acre over 25 acres, with the fee covering plan review and a set number of inspection hours.
A handful of activities are exempt, including disturbances under 5,000 square feet outside a common plan of sale, ordinary crop farming and tilling, permitted quarry operations, and emergency work needed to protect life or property, though the Director can revoke an exemption if erosion controls are not actually being used.
Violations & Fines
A violation of Chapter 505 is a misdemeanor carrying a minimum fine of $200, with each day a violation continues charged as a separate offense under Section 505.050(C). The Director of Public Works can enforce the chapter directly, issue a summons to appear in County Municipal Court, use the permit holder's performance guarantee to complete or repair erosion controls, and seek a court injunction to stop the work.
Frequently Asked Questions
How big does a project have to be before Jefferson County requires a land disturbance permit?
What does a Jefferson County land disturbance permit cost?
What happens if I disturb land without a Jefferson County permit?
Do farmers need a land disturbance permit to till their fields?
Sources & Official References
Other rules in Jefferson County
Compare Jefferson County to another location·View the Missouri environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.