Key Facts

Permit Threshold
50 cubic yards typical
Slope Rule
6 in fall in 10 ft
1-Acre Disturb
DEC SPDES GP
Common Law
Reasonable use
County Roads
DPW review

Summary

Grading permits required from Oneida County town code enforcement for cuts/fills over 50 cubic yards in most towns. Drainage must not alter natural flow onto adjacent properties per NY common law (reasonable use rule). County DPW reviews work affecting county drainage.

These county ordinances apply to unincorporated areas of Oneida County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

Throughout New York State, before commencing construction, the owner or operator of construction activities that will involve soil disturbance of one or more acres must obtain coverage under the State Pollutant Discharge Elimination System (SPDES) General Permit for Stormwater Discharges from Construction Activity, succinctly referred to as the Construction General Permit (CGP). Alternatively, the owner or operator of such construction activities must obtain coverage under an individual SPDES permit. In the New York City East of Hudson watershed, this requirement also applies to construction activities that will disturb 5,000 square feet or more, but less than one acre of land. In the municipal boundaries of the City of New York (NYC), this requirement also applies to construction activities that will disturb 20,000 square feet or more, but less than one acre of land, including less than 20,000 square feet which are part of a common plan of development or sale that will ultimately disturb 20,000 square feet or more, but less than one acre. In the municipal boundaries of NYC, this requirement also applies to construction activities that create 5,000 square feet or more of impervious area. Some exceptions to the requirements exist for agricultural projects, certain silvicultural projects, and routine maintenance activities. SPDES General Permit for Stormwater Discharges from Construction Activity, GP-0-25-001, Construction General Permit (CGP). This permit became effective on January 29, 2025, and expires on January 28, 2030.

Source: NY DEC SPDES ConstructionView official code

Full Breakdown

NY Residential Code R401.3 and NY Building Code 1804 require site grading to drain water away from structures at 6 inches of fall within 10 feet. Most Oneida County towns require a permit for grading over 50 cubic yards (Town of New Hartford Code 130-45, Town of Whitestown 175-26). Drainage follows NY common law reasonable-use rule (Kossoff v. Rathgeb-Walsh, 1958, 3 NY2d 583): upper owner may make reasonable use of their land even if it alters runoff, but must not cause unreasonable harm to lower owners. Sites disturbing 1+ acres require NY DEC SPDES General Permit GP-0-20-001 (construction stormwater) with SWPPP. Projects in or near NY DEC regulated freshwater wetlands (12.4+ acres) need Article 24 permits. Oneida County DPW (315-798-5766) reviews work affecting county roads and county drainage infrastructure. Impacts to Mohawk River or Oneida Lake tributaries may also trigger Army Corps 404 review.

Violations & Fines

Unpermitted grading: $250-$500 first offense plus stop-work. SPDES permit violation: up to $37,500 per day per NY ECL 71-1929. Drainage diversion causing damage: civil liability plus injunctive relief.

Frequently Asked Questions

Do I need a permit to regrade my yard?
Yes for cuts or fills over 50 cubic yards in most Oneida County towns; verify with local code enforcement.
Can my neighbor send runoff onto my property?
Not unreasonably. NY reasonable-use rule allows upper owner normal use but prohibits harmful diversion.
When does DEC get involved?
Land disturbance of 1+ acres requires SPDES General Permit GP-0-20-001 with Stormwater Pollution Prevention Plan.

Sources & Official References

Other rules in Oneida County

All Oneida County rules

New York rules heatmap·Compare Oneida County to another location·View the New York environmental rules overview

Get notified when Erosion Control in Oneida County, NY changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Erosion Control in Cities Across Oneida County