Skip to main content
CityRuleLookup

St. Charles County, MO Environmental Rules: Erosion Control (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Permit trigger
5,000 sq ft or more of land disturbance
Issuing agency
Dept. of Community Development, Development Review Division
Base plan review fee
$50 plus $50/acre up to 10 acres
Correction deadline
7 calendar days after notice to correct
Maximum fine
$1,000 per day, separate violation each day
Key exemption
Gardening on one- or two-family lots

Summary

St. Charles County requires a land disturbance permit before anyone disturbs 5,000 square feet or more of unincorporated ground for non-agricultural development. The Department of Community Development issues the permit, plan review runs $50 plus $50 per acre up to ten acres, and violators face a misdemeanor charge with fines up to $1,000 per day the disturbance continues unpermitted.

These county ordinances apply to unincorporated areas of St. Charles County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

Any person, firm, corporation or business proposing to remove any ground vegetation, to disturb or fill the land or to store soil within unincorporated St. Charles County shall apply to the Department of Community Development for approval and issuance of a land disturbance permit. State and Federal permit conditions that are more stringent than the requirements set forth herein shall govern. ... It shall be unlawful for the owner of a property and/or that owner's agent to perform land disturbance activities affecting five thousand (5,000) square feet or more without obtaining a land disturbance permit.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: rev 4863880; v61 updated 2026-05-11; through 05-11-2026).

Full Breakdown

St. Charles County Code Chapter 412 governs erosion and sediment control on unincorporated land undergoing non-agricultural development. 010 states the purpose is to control soil erosion, preserve natural terrain and waterways, and prevent degradation of water quality and obstruction of stormwater flows in storm sewers, road ditches and natural watercourses. 020 requires anyone proposing to remove ground vegetation, disturb or fill land, or store soil in the unincorporated county to apply to the Department of Community Development for a land disturbance permit; stricter state or federal permit conditions govern where they exceed the county standard.

040 sets the trigger: land disturbance activity affecting 5,000 square feet or more requires the permit before work starts. 050 exempts right-of-way work under a special use permit, public utility installation and repair, quarries and permitted landfills that do not drain off-site, farming and landscaping done to soil conservation standards, resodding under 10,000 square feet, ordinary gardening on one- and two-family lots, emergency work protecting life or property, and specified levee repairs, provided none of these change drainage patterns or cause sedimentation onto neighboring land.

130. A performance guarantee covering the cost of erosion and sediment controls must be posted before a permit issues and can be forfeited to fund pollution-prevention work if a violation goes uncorrected.

Violations & Fines

Failing to obtain the permit, failing to install required erosion and sediment controls, or ignoring a written notice to correct within its seven-calendar-day deadline is a violation under Section 412.140. The Director of Development Review can issue a stop-work order, and every day the violation continues is a separate offense. Violators are guilty of a misdemeanor punishable by a fine up to $1,000 per day, and the County Counselor may sue in Circuit Court for fines and injunctive relief.

Frequently Asked Questions

Does clearing brush on my St. Charles County lot need a permit?
Only if the disturbed area reaches 5,000 square feet or more under Section 412.040. Ordinary gardening on one- and two-family lots is exempt under Section 412.050(A)(6), and resodding or reseeding up to 10,000 square feet is exempt under Section 412.050(A)(5), as long as neither changes drainage or sends sediment onto a neighbor's property.
What does a St. Charles County land disturbance permit cost?
The Development Review Division charges a plan review fee based on disturbed acreage: $50 plus $50 per acre for the first acre through ten acres, $25 per acre from ten to twenty-five acres, and $10 per acre beyond twenty-five acres, plus a separate base inspection fee collected before the permit is issued.
What happens if I disturb land in St. Charles County without a permit?
The Director of Development Review issues a notice of violation with a stop-work order and starts fines accruing from the day the unauthorized disturbance began. Under Section 412.140(C)(3), violators are guilty of a misdemeanor and face fines up to $1,000 for every day the violation continues, and the County Counselor can seek an injunction in Circuit Court.
Are farming and utility work exempt from the erosion control permit?
Yes. Section 412.050 exempts farming, nurseries, landscaping and gardening done to local soil conservation standards, plus utility installation, inspection, repair or replacement work, quarries and permitted landfills that don't drain off-site, and emergency work needed to protect life, property or natural resources, provided drainage patterns and off-site sedimentation stay unchanged.

Sources & Official References

Other rules in St. Charles County

All St. Charles County rules

Compare St. Charles County to another location·View the Missouri environmental rules overview

Get notified when Erosion Control in St. Charles County, MO changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.