Key Facts

Cut slope trigger
Over 5 feet in height
Fill slope trigger
Over 3 feet in height
Enforcing agency
County Building Inspection Department
Planting timing
Installed after rough grading
Final approval standard
Growth must be established
Variance requires
Soil engineer or geologist recommendation

Summary

Contra Costa County's grading ordinance requires erosion protection on any cut slope over five feet or fill slope over three feet before a grading permit closes out. The county building inspection department requires planting with grass or ground cover suited to the site's soil and climate, installed after rough grading, with final sign-off withheld until growth is established on the slope.

City-specific rules exist: Brentwood, San Ramon, and Antioch have their own erosion control rules that differ from Contra Costa County's county-level regulations. If you live in one of those cities, check the city-specific page instead.

The surface of all erodible cut slopes more than five feet in height and fill slopes more than three feet in height shall be protected against erosion by planting with grass or ground cover plants. The plants and planting methods shall be suitable for the soil and climatic conditions of the site and in accordance with standard specifications on file in the county building inspection department... The planting shall be installed after rough grading. Final approval of the work shall be made when growth is established on the slopes... Variations from the regulations in Sections 716-8.802-716-8.806 may be allowed by the building official if they will provide equivalent safety, stability, and protection against erosion, as recommended by a soil engineer or engineering geologist.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Ordinance Code: Supplement 103).

Full Breakdown

8 of the county's Grading Ordinance (Division 716) governs erosion control planting on unincorporated land. 802 requires that erodible cut slopes taller than five feet and fill slopes taller than three feet be planted with grass or ground cover plants suited to the site's soil and climate, following standard specifications kept on file with the county building inspection department. 804, planting must go in after rough grading is complete, and the county building official will not give final approval on the work until growth is actually established on the slope, not merely seeded.

806, but it must be recommended in writing by a soil engineer or engineering geologist and approved by the building official; there is no automatic exemption. 612, which requires ongoing maintenance of drainage facilities during and after the work. 1008. These duties attach to any grading permit issued under Division 716 and are checked by county inspectors before the permit is closed.

Violations & Fines

If the county building official issues a written stop-work notice under Section 716-4.1432, the permittee must immediately cause all grading and hauling to cease until written permission to resume is granted, after correcting the erosion or drainage problem that triggered the notice. Under Section 716-6.016, a contractor who stops work before completion must still leave the site safe and free of erosion, landslide, or drainage hazards to adjoining property and public roads.

Frequently Asked Questions

Does every graded lot in unincorporated Contra Costa County need erosion planting?
Only if the job creates an erodible cut slope over five feet or a fill slope over three feet. Section 716-8.802 requires those slopes be planted with grass or ground cover suited to the site's soil and climate, per specifications on file with the county building inspection department; smaller slopes aren't covered by this planting duty.
When does the county sign off on erosion planting?
Not until growth is actually established on the slope. Section 716-8.804 requires planting after rough grading, and the county building official withholds final approval on the grading permit until the vegetation has taken, not simply been seeded or installed.
Can I skip the required planting if I use a different erosion method?
Only with a variance under Section 716-8.806, and only if a soil engineer or engineering geologist recommends the substitute in writing and the county building official agrees it gives equivalent safety, stability, and erosion protection to standard planting.
What happens if the county issues a stop-work order over erosion problems?
Under Section 716-4.1432, all grading and hauling on the site must stop immediately and stay stopped until the county building official issues written permission to resume, which only follows correction of the erosion hazard or violation that triggered the notice in the first place.

Sources & Official References

Other rules in Contra Costa County

All Contra Costa County rules

California rules heatmap·Compare Contra Costa County to another location·View the California environmental rules overview

Get notified when Erosion Control in Contra Costa County, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Erosion Control in Cities Across Contra Costa County