Shasta County, CA Environmental Rules: Erosion Control (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified August 2026

Key Facts

Applies to
Construction sites within MS4 permit area (Sec. 18.10.190(A))
Core requirement
Implement BMPs to max extent practicable
Covered activities
Grading, excavating, paving, vegetation removal
Permit conditions
BMP duties attach to grading/building permits
Inspection
Director may enter and test (Sec. 18.10.230, .250)
Fee violation
Unpaid inspection fees are a separate violation

Summary

Shasta County Code Section 18.10.190 requires anyone who owns or operates a construction site inside the county's MS4 permit area to install best management practices controlling pollutant discharge to the storm system, matching the state's Construction General Permit and the MS4 permit's Construction Site Storm Water Runoff Control Program to the maximum extent practicable.

City-specific rules exist: Redding has its own erosion control rules that differ from Shasta County's county-level regulations. If you live in Redding, check the city-specific page instead.

Any person owning or operating a construction site within an MS4 permit area shall implement BMPs to control the discharge of pollutants to the county storm water conveyance system or receiving waters to the MEP in compliance with Section E.10, "Construction Site Storm Water Runoff Control Program," of the MS4 permit, the construction general permit and applicable county requirements.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code: Supplement 22).

Full Breakdown

10's storm water program adopted by Ordinance No. " Any such site inside the county's designated "MS4 permit area" must implement BMPs, meaning "schedules of activities, prohibitions of practices, maintenance procedures, and other management practices" that prevent or reduce pollutant discharge to the maximum extent practicable, consistent with the state's Construction General Permit administered under the Clean Water Act and Porter-Cologne Water Quality Control Act. 190(B) lets the county fold these BMP duties into development standards, permit conditions, or conditions of approval, so a grading or building permit can carry site-specific erosion and sediment control conditions enforceable as code violations.

250 to confirm BMPs are working. 270 authorizes the board of supervisors to set inspection and administration fees by resolution, and failure to pay those fees within the deadline the director sets is itself a separate violation of the chapter.

Violations & Fines

A construction site discharging sediment or other pollutants in violation of Section 18.10.190 faces the same enforcement as any other Chapter 18.10 violation: a notice of non-compliance, an immediate cease-and-desist order under Section 18.10.290 for threats to receiving waters, county abatement billed to the violator, and, through Section 18.10.280's cross-reference to Chapter 1.08, escalation to a misdemeanor with up to a $1,000 fine and one year in jail after a third violation in 12 months.

Frequently Asked Questions

What construction activities trigger Shasta County's erosion control rule?
Section 18.10.020 defines "construction activity" broadly: grading, digging, cutting, scraping, stockpiling, excavating soil, placing fill, paving or removing pavement, demolition, and any substantial removal of vegetation that disturbs soil or bares rock. Any construction site meeting that definition inside the county's MS4 permit area must follow Section 18.10.190's BMP requirement.
What must a builder actually do to comply?
The builder must implement best management practices, defined in Section 18.10.020 as schedules of activities, prohibitions, maintenance procedures, and structural or source controls, that reduce pollutant discharge to the maximum extent practicable, matching the state's Construction General Permit and the county's own permit conditions issued under Section 18.10.190(B).
What happens if a construction site doesn't control its runoff?
The resource management or public works director can inspect the site under Section 18.10.230, issue a notice of non-compliance, and order an immediate cease and desist under Section 18.10.290 if the runoff threatens receiving waters, with abatement costs and escalating misdemeanor fines up to $1,000 for repeat violations.

Sources & Official References

Other rules in Shasta County

All Shasta County rules

California rules heatmap·Compare Shasta County to another location·View the California environmental rules overview

Get notified when Erosion Control in Shasta County, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Erosion Control in Cities Across Shasta County