Harrison County, MS Environmental Rules: Erosion Control (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Permit trigger
New development or >1 acre disturbance
Approving authority
Harrison County Engineer
Precondition
No building permit without approved DMSP
DMSP submittal fee
None required
Variance available
Yes, via County Engineer, § 1012.04.02
Coverage
Unincorporated Harrison County only

Summary

No building permit or final subdivision plat can be issued in unincorporated Harrison County until the County Engineer approves a Drainage Management Site Plan, a requirement that applies to every new residential, commercial or industrial development and to any grading that disturbs more than one acre.

These county ordinances apply to unincorporated areas of Harrison County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

A Drainage Management Site Plan (DMSP) shall be required for any new single-family residential developments and for any new commercial, multi-family residential, institutional, industrial, or utility developments, and shall be required for land disturbing activities greater than one acre. ... No final subdivision plat shall be approved and no building permits shall be issued until and unless a DMSP or lesser plan as required by the County Engineer has been reviewed and approved by the County Engineer.

View official code

Official source re-checked September 7, 2026: the cited page had not changed since it was quoted.

Full Breakdown

01 sets the permit trigger for the county's Drainage Management Site Plan (DMSP): it applies to any new single-family residential development, any new commercial, multi-family residential, institutional, industrial or utility development, and any land-disturbing activity greater than one acre. Older platted lots and non-platted single-family sites are exempt from a full plan unless the County Engineer requests one, and the code allows a scaled-down 'lesser plan' for qualifying individual residential properties, with the level of detail set by the County Engineer. The Engineer can also require a DMSP for any grading or excavation that would fill, obstruct, or otherwise alter a creek, stormwater channel or drainage facility, even outside the categories above, if adverse impacts are anticipated.

The plan itself must be sealed by a professional engineer registered in Mississippi and must include a topographic survey, existing sewer locations, projected runoff volumes, and a layout of the proposed drainage structures. Separately, an Encroachment Permit is required for any private entrance or utility work performed in the county road right-of-way, with the Utility Permit fee refunded if the work is completed as permitted within one year. This permit scheme applies only to unincorporated Harrison County, not to Gulfport, Biloxi, Long Beach, Pass Christian or D'Iberville.

Violations & Fines

Building or grading without an approved DMSP, or without completing the improvements it requires, triggers a Notice of Violation from the County Engineer or Road Department, giving the violator 10 days to fix the listed deficiencies. Continued noncompliance can bring a citation, a Stop Work Order covering all construction on the site except corrective work, and revocation of the Utility Permit with forfeiture of its bond. Section 1012.05.04 makes conviction a misdemeanor punishable by a $25-$250 fine and/or one day's imprisonment, with each day of the ongoing violation a separate offense; a person who refuses to finish the required work must also reimburse the county for completing it. Appeals go to the Board of Supervisors within 30 days of the notice.

Frequently Asked Questions

Do I need a drainage permit to build a house on an existing platted lot?
Not necessarily. Section 1012.02.01 exempts non-platted single-family home sites and older platted lots without a prior drainage analysis from the full DMSP unless the County Engineer specifically requests one, though a scaled-down 'lesser plan' can still be required.
What size project needs a full Drainage Management Site Plan?
Any new commercial, multi-family, institutional, industrial or utility development, any new single-family subdivision, and any land-disturbing activity exceeding one acre must have an approved DMSP before a building permit or final plat is issued.
Can the county require a plan for grading that isn't new construction?
Yes. Section 1012.02.01 lets the County Engineer require a DMSP before any grading or excavation that would fill, obstruct or otherwise alter a creek, stormwater channel or drainage facility, whenever adverse impacts are anticipated.
Is a separate permit needed for a driveway entrance onto a county road?
Yes, an Encroachment Permit is required for a private entrance or utility work in the county right-of-way, and the accompanying Utility Permit fee is refunded only if the work is completed as specified within one year of issuance.

Sources & Official References

Other rules in Harrison County

All Harrison County rules

Compare Harrison County to another location·View the Mississippi environmental rules overview

Get notified when Erosion Control in Harrison County, MS changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.