Key Facts

Trigger
any clearing, grading, or filling
Design standard
FDEP Erosion & Sedimentation Control Manual
Secondary standard
FDOT Drainage Manual specifications
Maintenance
continuous through construction phase
Spring/sinkhole buffer
15 ft natural vegetation, Sec. 3502
Coverage
unincorporated Citrus County only

Summary

Before clearing, grading, or filling a development site in unincorporated Citrus County, the Land Development Code requires an approved erosion and sediment control plan matching the state's Stormwater Erosion and Sedimentation Control Inspector's Manual, and bars any land disturbance until those measures are installed and maintained through construction.

These county ordinances apply to unincorporated areas of Citrus County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

K. Erosion and Sedimentation Control. Proposed temporary and permanent erosion and sediment control plans shall be submitted with each application for development approval. These plans shall specify in detail the erosion and sedimentation control measures to be used during all phases of clearing, grading, filling, construction and permanent development, and accurately describe their proposed operation. In addition, these plans shall be in accordance with the latest applicable specifications and recommendations as contained in the Florida DEP's (FDEP's) publication, "Florida Stormwater Erosion and Sedimentation Control Inspectors Manual", latest edition and the State of Florida Department of Transportation (FDOT Drainage Manual). No clearing, grading, excavating, filling, or other disturbing of the natural terrain will be permitted until County-approved erosion and sediment control measures have been installed. All erosion and sediment control measures shall be continuously maintained during the construction phase of the development.

Full Breakdown

Sec. 6220(K) of Chapter Six, Stormwater Management, of the Citrus County Land Development Code, "Erosion and Sedimentation Control," requires every development application to include temporary and permanent erosion and sediment control plans specifying the measures to be used during clearing, grading, filling, construction, and permanent development, and describing how they'll operate. The plans must follow the Florida Department of Environmental Protection's "Florida Stormwater Erosion and Sedimentation Control Inspectors Manual" and the Florida Department of Transportation's Drainage Manual. No clearing, grading, excavating, or filling of natural terrain is allowed until the county has approved and the applicant has installed the required measures, and those measures must be continuously maintained during the entire construction phase, covering street and utility work as well as protection of individual lots.

Parcels next to a spring, spring run, or sinkhole open to the aquifer carry an added layer under Sec. 3502: a separate Erosion Plan built to the same FDOT/FDEP manual, erosion control barriers unless a 15-foot natural vegetation buffer is retained, and prompt seeding, sodding, or mulching of any ground cleared before construction begins, reflecting the county's karst, spring-fed hydrology around Crystal River. A related rule, Sec. 6220(J), separately bars grading, stockpiling, or excavating that changes surface drainage to a neighboring property's detriment. Applies only in unincorporated Citrus County; Crystal River and Inverness enforce their own stormwater and erosion codes.

Violations & Fines

Growth Management withholds or revokes development approval until erosion controls are inspected and confirmed installed under Sec. 6220(K). Site disturbance that proceeds without approved measures, or that damages a neighbor's drainage under Sec. 6220(J), is enforceable through the LDC's general penalties chapter (Sec. 1800), including stop-work orders and civil injunctive action in circuit court to force compliance or restoration.

Frequently Asked Questions

Do I need an erosion control plan before grading my lot in Citrus County?
Yes. LDC Sec. 6220(K) requires a temporary and permanent erosion and sediment control plan with every development application, and no clearing, grading, excavating, or filling is allowed until the county has approved the plan and the measures are installed.
What standard does the county use for erosion control designs?
Sec. 6220(K) ties the plan to the Florida DEP's "Florida Stormwater Erosion and Sedimentation Control Inspectors Manual" and the Florida DOT Drainage Manual, so contractors must design ground cover, barriers, and sediment controls to those state specifications, not an informal standard.
Are there extra rules near Crystal River's springs?
Yes. Sec. 3502 adds a separate erosion plan requirement for projects next to a spring, spring run, or sinkhole open to the aquifer, plus erosion control barriers unless a 15-foot natural vegetation buffer stays in place, and prompt seeding or mulching of any ground cleared before construction starts.
What if grading on my property damages my neighbor's drainage?
Sec. 6220(J) separately bars stockpiling, grading, or excavating that changes surface drainage patterns to a neighboring property's detriment, including concentrating or redirecting stormwater flow; the county can pursue this independently of whether your erosion control plan was approved.

Sources & Official References

Other rules in Citrus County

All Citrus County rules

Florida rules heatmap·Compare Citrus County to another location·View the Florida environmental rules overview

Get notified when Erosion Control in Citrus County, FL changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.