Knox County, TN Environmental Rules: Erosion Control (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Governing sections
Sec. 26-251 and 26-252, Knox County Code
Applies to
All land-disturbing activity, even plan-exempt work
Design standard
State NPDES construction general permit
Conflict rule
Stricter standard controls
Bond release
Only after final site stabilization

Summary

Any construction or land-disturbing activity in unincorporated Knox County, even work exempt from a stormwater plan, must run erosion prevention and sediment control under Sec. 26-251 to stop off-site sedimentation. Sec. 26-252 ties the required best management practices to the state's NPDES construction general permit and the county's own stormwater manual, whichever standard is stricter.

City-specific rules exist: Knoxville has its own erosion control rules that differ from Knox County's county-level regulations. If you live in Knoxville, check the city-specific page instead.

In keeping with [this] section, adequate erosion prevention and sediment control measures shall be employed consistent with guidance materials referenced herein for all land disturbing activities, including those exempted in section 26-171 to minimize erosion and prevent off-site sedimentation. Land disturbing or construction activities that do not employ erosion prevention and sediment controls and cause off-site sedimentation or sediment discharges to waters of the state or onto adjacent properties may be subject to enforcement. (Sec. 26-251) ... (a)Operators shall implement appropriate erosion prevention and sediment control best management practices. (Sec. 26-252(a))

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 23).

Full Breakdown

Sec. 26-251, part of the county's Division 5 erosion prevention and sediment control rules, requires "adequate erosion prevention and sediment control measures" on all land-disturbing activities, including projects exempted from filing a full stormwater management plan under Sec. 26-171, specifically to keep sediment from leaving the site or reaching state waters. Operators failing to install controls and causing off-site sedimentation are subject to enforcement. Sec. 26-252 spells out how: design, installation, maintenance and inspection must follow the State of Tennessee NPDES General Permit for construction stormwater, the TDEC erosion and sediment control handbook, and the county's own stormwater management manual, and wherever these conflict, the stricter standard controls.

Sites discharging into impaired or exceptional Tennessee waters, and "priority construction activities," face additional requirements, and the director can demand more stringent controls where a threatened or endangered species' habitat is at risk. Sediment basin and trap discharges must run through a pipe or a rip-rap-lined spillway so they do not cause erosion, and sediment-laden water pumped from excavations must be held in a settling basin or filtered before release, discharged only onto a stabilized outlet point. Construction site operators must also control other construction wastes, such as discarded building material, concrete truck washout and sanitary waste, that could harm water quality.

The erosion-control portion of a project's performance bond is released only after the site reaches final stabilization under the state general permit, and the director can hold it longer or demand extra measures on a priority site or one with a history of off-site sediment damage.

Violations & Fines

Land-disturbing or construction work that skips required erosion and sediment controls and causes off-site sedimentation or a discharge to state waters "may be subject to enforcement" under Sec. 26-251, which routes into the stormwater ordinance's penalty scheme: civil penalties of $250.00 to $5,000.00 per day under Sec. 26-157, plus stop-work orders and withheld permits.

Frequently Asked Questions

Do small projects skip erosion control requirements?
No. Sec. 26-251 requires erosion prevention and sediment control on all land-disturbing activities, including those exempt from filing a stormwater management plan under Sec. 26-171. Skipping controls and causing sediment to leave the site or reach state waters exposes the operator to enforcement under the stormwater ordinance regardless of the project's size.
What standards govern erosion control design in Knox County?
Sec. 26-252 requires design, installation, maintenance and inspection to follow the State of Tennessee NPDES General Permit for construction stormwater discharges, the TDEC erosion and sediment control handbook, and the county's own stormwater management manual, applying whichever of these sets the stricter or higher standard when they conflict or overlap.
When is my erosion-control performance bond released?
The erosion-control portion of the performance bond is released only after the site reaches final stabilization under the State of Tennessee NPDES general permit, per Sec. 26-252(k). On a priority construction site, or one with a record of off-site sediment damage, the director can require stricter stabilization before releasing that bond.

Sources & Official References

Other rules in Knox County

All Knox County rules

Compare Knox County to another location·View the Tennessee environmental rules overview

Get notified when Erosion Control in Knox County, TN changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Erosion Control in Cities Across Knox County