Benton County, AR Environmental Rules: Erosion Control (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

SWP3 threshold
1 acre or more disturbed
Subdivision lots
count toward whole platted area
BMP inspection cadence
every 7 days, or every 14
Reviewing officer
Environmental Affairs Officer
Enforcement tools
stop-work order, performance bond
Coverage area
MS4 unincorporated urbanized area only
Adopted
Quorum Court Ord. O-2023-53, 2023

Summary

Any construction site in unincorporated Benton County that disturbs an acre or more of soil, including a single lot inside a bigger subdivision, needs a certified Stormwater Pollution Prevention Plan before work starts. The county's Environmental Affairs Officer reviews it, and Planning staff won't clear the site for construction until it's filed.

These county ordinances apply to unincorporated areas of Benton County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

This provision applies to all construction sites where construction on a site will disturb soil or remove vegetation on one (1) or more acres of land during the life of the construction project; this shall include a single lot in a subdivision regardless of size. A Stormwater Pollution Prevention Plan (SWP3) for the project must be provided and implemented by the construction site owner as follows: 1. The area disturbed shall be assumed to include the entire property area unless all applicable plans specifically exclude certain areas from disturbance. 2. The SWP3 must be provided by the owner and filed with the appropriate staffer. For sites subject to review by the Planning Board such will not be approved for construction until a duly certified SWP3 has been filed with the appropriate staffer. 3. The Environmental Affairs Officer may require revisions to the SWP3. Construction activity, including any soil disturbance or removal of vegetation, shall not commence on the site until a duly certified SWP3 has been filed with the appropriate staffer.

View official code

Official source re-checked September 7, 2026: the cited page had not changed since it was quoted.

Full Breakdown

Chapter VIII's stormwater program requires every construction site to control erosion and sediment with Best Management Practices, and sets a hard numeric trigger for a written plan. 3(B)). 3(B)(3)). 3(C)). 3(D)(2)). 7, item 12). 4(J)).

Violations & Fines

Noncompliance draws a Notice of Violation from Planning staff, the Environmental Affairs Officer or the County Engineer, followed by a stop-work order that halts all site activity except corrective work (§8.4(D)). The county can also require a performance bond payable to Benton County, which the owner may protest to the County Judge within 15 calendar days (§8.4(F)), and the County Judge can sue for an injunction, damages, costs and attorney fees (§8.4(I)). A violation that is also a state offense is punishable under A.C.A. § 8-4-105 (§8.4(G)).

Frequently Asked Questions

Does a half-acre lot inside a subdivision need a stormwater plan?
Yes, if the subdivision as a whole disturbs an acre or more. The ordinance measures the SWP3 threshold against the entire platted area, and it specifically includes "a single lot in a subdivision regardless of size," so an individual half-acre lot still has to comply with the development's approved plan.
Who reviews the SWP3 before construction can start?
The county's Environmental Affairs Officer reviews it and can require revisions, and Planning staff will not approve a site for construction until a duly certified SWP3 is on file. Soil disturbance or vegetation removal is barred until that certification happens.
How often do erosion controls have to be inspected once installed?
At least once every seven days, or every 14 calendar days combined with an inspection within 24 hours after any quarter-inch-or-greater rainfall. Any Best Management Practice that isn't working has to be modified within 24 hours of discovery and corrected within 7 calendar days.
What can the county do if a builder ignores erosion control requirements?
Planning staff or the Environmental Affairs Officer can issue a stop-work order halting all site activity except corrective measures, require a bond to guarantee compliance, and the County Judge can go to court for an injunction, damages and attorney fees.

Sources & Official References

Other rules in Benton County

All Benton County rules

Compare Benton County to another location·View the Arkansas environmental rules overview

Get notified when Erosion Control in Benton County, AR changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.