Key Facts

Applies to
Grading in unincorporated Monterey County
Default method
Fast-germinating planting, e.g. rye grass
Deadline
Installed before final inspection
Backup method
Check dams, cribbing or riprap
Includes
Dust control on the grading site

Summary

Monterey County Code Section 16.08.340 requires anyone grading land in the unincorporated county to prepare and maintain disturbed surfaces to control erosion, using fast-germinating plantings such as rye grass or barley installed before final inspection. The Building Official can require watering to establish growth or order check dams, cribbing or riprap where planting alone will not hold the slope, and must also control dust from the grading operation.

City-specific rules exist: Salinas has its own erosion control rules that differ from Monterey County's county-level regulations. If you live in Salinas, check the city-specific page instead.

All disturbed surfaces resulting from grading operations shall be prepared and maintained to control erosion. This control may consist of effective planting, such as rye grass, barley or some other fast germinating seed. The protection for the slopes shall be installed as soon as practicable and prior to calling for final inspection.

The Building Official may require watering of planted areas to assure growth.

Where it is determined by the Building Official that cut slopes are not subject to erosion due to the erosion-resistant character of the materials, such protection may be omitted.

Check dams, cribbing, riprap or other devices or methods shall be employed to control erosion.

Dust from grading operation must be controlled. The owner or contractor may be required to keep adequate equipment on the grading site to prevent dust problems.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 56).

Full Breakdown

08, Grading, which the county administers only in the unincorporated area; Salinas, Monterey, Seaside, Marina, Carmel-by-the-Sea, Pacific Grove and King City run their own grading codes. The section applies to 'all disturbed surfaces resulting from grading operations,' and the default compliance method is effective planting, naming rye grass and barley as examples of fast-germinating seed. 040. The Building Official retains two discretionary powers: requiring supplemental watering of planted areas to assure the vegetation actually establishes, and waiving the planting requirement altogether where cut slopes are made of erosion-resistant material that does not need cover.

Where vegetation alone will not hold a slope, the section requires 'check dams, cribbing, riprap or other devices or methods' to control erosion, giving the county latitude to demand engineered solutions on steeper or more erodible sites. The same section folds in dust control, making the owner or contractor responsible for keeping adequate equipment on site to prevent dust problems during the grading operation. 300's requirement that any area cleared of vegetation but not graded within thirty days be replanted under this same section to prevent uncontrolled erosion.

Violations & Fines

Grading operations that leave disturbed slopes unprotected violate Section 16.08.340 and face the same enforcement as any other grading violation: a stop-work notice under Section 16.08.430, written notice giving ten days to correct the erosion control deficiency, and a halt to all work until compliance is restored. The Building Official can also condition final map or other approvals on proper re-compaction and revegetation of disturbed soil.

Frequently Asked Questions

Does Monterey County require erosion control during grading?
Yes. Section 16.08.340 requires every disturbed surface left by a grading operation in the unincorporated county to be prepared and maintained to control erosion, with fast-germinating planting such as rye grass or barley named as the standard method and required to be installed before the final grading inspection is called.
Can the county require more than planting to stop erosion in Monterey County?
Yes. Where the Building Official determines that planting will not adequately protect a slope, Section 16.08.340 authorizes requiring check dams, cribbing, riprap or other erosion-control devices instead of, or in addition to, vegetation. The Building Official can also require supplemental watering to make sure planted erosion control actually establishes and holds the slope.
What happens if a graded slope in Monterey County is left without erosion control?
The Building Official can post the site with a stop-work notice under Section 16.08.430, require the deficiency corrected in writing within ten days, and halt further work until the erosion control required by Section 16.08.340 is in place. Final map or other approvals can also be withheld until the ground is re-compacted and revegetated.

Sources & Official References

Other rules in Monterey County

All Monterey County rules

California rules heatmap·Compare Monterey County to another location·View the California environmental rules overview

Get notified when Erosion Control in Monterey County, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Erosion Control in Cities Across Monterey County