Monterey County, CA Environmental Rules: Erosion Control (2026)
Key Facts
- Applies to
- Grading in unincorporated Monterey County
- Default method
- Fast-germinating planting, e.g. rye grass
- Deadline
- Installed before final inspection
- Backup method
- Check dams, cribbing or riprap
- Includes
- Dust control on the grading site
Summary
Monterey County Code Section 16.08.340 requires anyone grading land in the unincorporated county to prepare and maintain disturbed surfaces to control erosion, using fast-germinating plantings such as rye grass or barley installed before final inspection. The Building Official can require watering to establish growth or order check dams, cribbing or riprap where planting alone will not hold the slope, and must also control dust from the grading operation.
All disturbed surfaces resulting from grading operations shall be prepared and maintained to control erosion. This control may consist of effective planting, such as rye grass, barley or some other fast germinating seed. The protection for the slopes shall be installed as soon as practicable and prior to calling for final inspection.
The Building Official may require watering of planted areas to assure growth.
Where it is determined by the Building Official that cut slopes are not subject to erosion due to the erosion-resistant character of the materials, such protection may be omitted.
Check dams, cribbing, riprap or other devices or methods shall be employed to control erosion.
Dust from grading operation must be controlled. The owner or contractor may be required to keep adequate equipment on the grading site to prevent dust problems.
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 56).
Full Breakdown
08, Grading, which the county administers only in the unincorporated area; Salinas, Monterey, Seaside, Marina, Carmel-by-the-Sea, Pacific Grove and King City run their own grading codes. The section applies to 'all disturbed surfaces resulting from grading operations,' and the default compliance method is effective planting, naming rye grass and barley as examples of fast-germinating seed. 040. The Building Official retains two discretionary powers: requiring supplemental watering of planted areas to assure the vegetation actually establishes, and waiving the planting requirement altogether where cut slopes are made of erosion-resistant material that does not need cover.
Where vegetation alone will not hold a slope, the section requires 'check dams, cribbing, riprap or other devices or methods' to control erosion, giving the county latitude to demand engineered solutions on steeper or more erodible sites. The same section folds in dust control, making the owner or contractor responsible for keeping adequate equipment on site to prevent dust problems during the grading operation. 300's requirement that any area cleared of vegetation but not graded within thirty days be replanted under this same section to prevent uncontrolled erosion.
Violations & Fines
Grading operations that leave disturbed slopes unprotected violate Section 16.08.340 and face the same enforcement as any other grading violation: a stop-work notice under Section 16.08.430, written notice giving ten days to correct the erosion control deficiency, and a halt to all work until compliance is restored. The Building Official can also condition final map or other approvals on proper re-compaction and revegetation of disturbed soil.
Frequently Asked Questions
Does Monterey County require erosion control during grading?
Can the county require more than planting to stop erosion in Monterey County?
What happens if a graded slope in Monterey County is left without erosion control?
Sources & Official References
Other rules in Monterey County
California rules heatmap·Compare Monterey County to another location·View the California environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.