Arapahoe County, CO Environmental Rules: Erosion Control (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified August 2026

Key Facts

Permit required
GESC Permit for regulated land disturbance
Applies to
Unincorporated Arapahoe County only
Timing
Obtain before land disturbance starts
Coordination
Issued before or with building permit
Governing manual
Arapahoe County GESC Manual (adopted by reference)
Enforcing agency
PWD Director under the Board of Commissioners
Violation type
Zoning violation, enforcement action by county

Summary

Unincorporated Arapahoe County requires a Grading, Erosion and Sediment Control (GESC) permit before any regulated land disturbance begins. The permit, issued under the county's GESC Manual, applies countywide outside incorporated cities and must be secured before or alongside your building permit: skipping it is a zoning violation.

City-specific rules exist: Aurora, and Centennial have their own erosion control rules that differ from Arapahoe County's county-level regulations. If you live in one of those cities, check the city-specific page instead.

b. Applicability i. These Regulations shall apply to all property within the unincorporated areas of Arapahoe County. ii. No land disturbance shall occur on any property, unless otherwise exempted via provisions in the GESC Manual without first obtaining a GESC permit from the County. Such permit is subject to all applicable fees. iii. Persons proposing to conduct regulated land disturbance activities must apply for a GESC permit... A GESC permit shall be obtained prior to the start of the land disturbing activities even if a Federal or State agency or other jurisdiction has approved the project and issued a permit. 2. PROCEDURAL REQUIREMENTS a. Anyone proposing an activity requiring a GESC permit, as described in the GESC Manual, shall submit the required information as detailed in the GESC Manual, along with all applicable permit fees. No person shall engage in any regulated land disturbance activity without first obtaining a GESC permit. A GESC permit must be issued prior to or concurrent with the issuance of a building permit.

Source: CDPHE Stormwater Construction PermitView official code

Full Breakdown

" The regulations apply to all property within the unincorporated areas of Arapahoe County, and no land disturbance may occur without first obtaining a GESC permit from the county unless the GESC Manual exempts it, the permit carries its own applicable fees. Anyone proposing a regulated land-disturbance activity, including construction of a temporary batch plant, must apply for a GESC permit (or a Temporary Batch Plant GESC permit) and obtain it before land-disturbing work starts, even if a federal or state agency has already approved the project.

A GESC permit must be issued prior to or concurrent with the building permit, and the applicant must submit the information the GESC Manual requires along with all fees. Even projects exempt from GESC permitting must still use Best Management Practices (BMPs) for any clearing, grading, or land disturbance. 3, Tree Preservation. The county reviews GESC plan submittals for general compliance, but acceptance does not relieve the owner or designer of responsibility for their calculations, plans, specifications, or as-built work, nor does it excuse compliance with other federal, state, or local rules, where a federal or state standard is stricter, the more restrictive requirement controls. The GESC Manual itself can be amended by the Board of County Commissioners on recommendation of the PWD Director or Planning Commission.

Violations & Fines

The Board of County Commissioners, acting through the Public Works and Development (PWD) Director, enforces § 5-4.2. Failure to comply with any term, condition, limit, or deadline of the GESC Manual or a GESC permit, or failure to obtain a GESC permit at all, is treated as a zoning violation subject to county enforcement action, separate from any building-permit consequences.

Frequently Asked Questions

Do I need a permit to disturb land in unincorporated Arapahoe County?
Yes. Under LDC § 5-4.2, no land disturbance may occur on any property in unincorporated Arapahoe County unless the GESC Manual exempts it, and a GESC permit, with its applicable fees, must be obtained from the county first.
Does an approved federal or state permit excuse me from the county GESC permit?
No. Section 5-4.2.b.iii states a GESC permit must be obtained before land-disturbing activity starts "even if a Federal or State agency or other jurisdiction has approved the project and issued a permit," so the county permit is a separate requirement.
If my project is exempt from the GESC permit, do I still need erosion controls?
Yes. The LDC says that even if a project is exempt from GESC permitting, Best Management Practices are "still required for any clearing, grading, or land disturbing activities in accordance with the standards set forth in the GESC Manual."
What happens if I skip the GESC permit?
Failure to obtain a required GESC permit, or to comply with its terms or the GESC Manual, is a zoning violation that the PWD Director enforces on behalf of the Board of County Commissioners under LDC § 5-4.2.9.

Sources & Official References

Other rules in Arapahoe County

All Arapahoe County rules

Compare Arapahoe County to another location·View the Colorado environmental rules overview

Get notified when Erosion Control in Arapahoe County, CO changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Erosion Control in Cities Across Arapahoe County