Key Facts

First elevation check
Certificate filed at lowest floor, before framing (Sec. 8:905)
Second elevation check
Required again before certificate of occupancy (Sec. 8:912)
Flood map source
1993 FEMA Flood Insurance Study, FIRM/FBFM maps (Sec. 15:7)
Freeboard figure
Set by IBC Sec. 1612.5, not restated locally
Map disputes
Floodplain administrator resolves boundary conflicts (Sec. 15:7)

Summary

In FEMA-mapped flood hazard areas of East Baton Rouge Parish, Sec. 8:905 of the Code of Ordinances requires an elevation certificate for the lowest floor before vertical construction continues, and Sec. 8:912 requires that documentation again before a certificate of occupancy issues. Sec. 15:7 adopts the 1993 Flood Insurance Study maps that define which areas are regulated.

These county ordinances apply to unincorporated areas of East Baton Rouge Parish. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

In flood hazard areas, upon placement of the lowest floor, including the basement, and prior to further vertical construction, the elevation certification required in section 1612.5 of the International Building Code shall be submitted to the building official.

Full Breakdown

East Baton Rouge Parish ties its lowest-floor elevation rule to the International Building Code rather than setting its own freeboard number in the parish code. Sec. 5 of the International Building Code shall be submitted to the building official. That means construction on a flood-hazard lot must stop at the lowest floor until the certified elevation is filed and accepted; only then can framing continue. Sec. 5 of the International Building Code or applicable flood hazard provisions of the International Residential Code shall be submitted to the building official prior to issuance of the certificate of occupancy, so a project cannot get its occupancy sign-off without a second, confirming elevation submittal.

Which lots count as flood hazard areas in the first place is set by Sec. 15:7 of Title 15, which points to the areas of special flood hazard identified by the Federal Emergency Management Agency in a scientific and engineering report entitled The Flood Insurance Study for East Baton Rouge Parish, Baton Rouge and Vicinity, dated May 17, 1993, with accompanying flood insurance rate maps and flood boundary-floodway maps, and lets the floodplain administrator resolve any conflict between a mapped boundary and actual field conditions.

The parish code does not print a numeric freeboard figure itself; that number sits inside IBC Sec. 5, which the ordinance adopts by cross-reference rather than restating.

Violations & Fines

Framing beyond the lowest floor without filing the Sec. 8:905 elevation certificate leaves a project unable to pass its next inspection under the general approval bar in Sec. 8:919, and skipping the Sec. 8:912 documentation blocks issuance of the certificate of occupancy required by Sec. 8:1000 before the structure may be used or occupied.

Frequently Asked Questions

Does East Baton Rouge Parish require a flood elevation certificate?
Yes, twice. Sec. 8:905 requires the lowest-floor elevation certificate under IBC Sec. 1612.5 once the lowest floor is placed and before any further vertical construction, and Sec. 8:912 requires the same documentation again before the building official issues a certificate of occupancy.
How does the parish decide which lots are in a flood hazard area?
Sec. 15:7 adopts the FEMA-prepared Flood Insurance Study for East Baton Rouge Parish, Baton Rouge and Vicinity, dated May 17, 1993, along with its flood insurance rate maps and flood boundary-floodway maps, and lets the floodplain administrator resolve conflicts against actual field conditions.
Does the parish code set its own freeboard height above base flood elevation?
No. Sec. 8:905 and Sec. 8:912 both point to section 1612.5 of the International Building Code for the elevation standard rather than printing a separate parish freeboard number, so the applicable height comes from the adopted IBC provision.

Sources & Official References

Other rules in East Baton Rouge Parish

All East Baton Rouge Parish rules

Compare East Baton Rouge Parish to another location·View the Louisiana environmental rules overview

Get notified when Flood Elevation Requirements in East Baton Rouge Parish, LA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Flood Elevation Requirements in Cities Across East Baton Rouge Parish