Taylor County, TX Environmental Rules: Flood Elevation Requirements (2026)
Key Facts
- Freeboard minimum
- 12 inches above base flood elevation
- Certified by
- registered professional engineer's seal
- Disclosed to buyers
- flood-plain status, BFE, floor elevation
- Permit required
- Development Permit, County Environmental Dept.
- Enforcing office
- Development/Permitting, 325-674-1235
- Governing sections
- Art. VI §6.03(4); Art. IX §§9.01-9.03
Summary
Taylor County requires final subdivision plats in flood hazard areas to certify that finished floor elevations sit at least 12 inches above the base flood elevation (BFE). A licensed engineer must seal the statement, and Article IX makes sellers disclose the tract's flood-plain status, BFE, and minimum floor elevation before closing.
“A flood hazard study has been performed and the development in the proposed subdivision will not adversely affect the interior or exterior storm water drainage or adjacent property owners. Base flood elevations (BFE) have been determined and Taylor County requires 12 inches above BFE as minimum to build elevation in a flood hazard area.”
Full Breakdown
03(4) of the Taylor County Development Procedures and Regulations requires every final plat covering land where a flood study was performed, whether a full or limited study, to carry a certified statement disclosing the flood hazard finding. The statement itself sets the numeric standard: Taylor County requires 12 inches above BFE as minimum to build elevation in a flood hazard area, and it must appear over the seal of the responsible public engineer, not just a staff signature. Article IX backs that plat statement with disclosure duties running to the next owner.
01 requires the plat to delineate how much of the subdivision lies in the flood plain. 02 requires any subdivision inside the county's flood plain management area to show compliance with those regulations before the plat is approved, and it requires the subdivider to tell a prospective buyer three specific things: whether the tract sits in a flood plain, the base flood elevation, and the minimum finished floor elevation. 03 goes further for lots in an identified flood hazard area: the owner must inform each prospective buyer in writing that a Development Permit from the Taylor County Environmental Department will be required before any structure can be placed on the property.
04 lets the Commissioners' Court withhold final plat action until requirements are met, a subdivider who omits the freeboard certification or the buyer disclosures can see plat approval delayed past the standard 60-day review clock. The Development/Permitting office (325-674-1235) and the Environmental Department administer both the plat-stage certification and the building-stage Development Permit.
Violations & Fines
A plat missing the sealed 12-inch freeboard statement or the flood-plain disclosures required by Art. IX §§ 9.01-9.03 will not clear Commissioners' Court review under the 60-day action clock in Art. VI § 6.04; the Commissioner can list it among the reasons for disapproval. Building below the certified elevation without the required Development Permit exposes the owner to permit denial and loss of flood-insurance eligibility for the structure.
Frequently Asked Questions
Does Taylor County require homes to be built above the base flood elevation?
What must a subdivider tell a buyer about flood risk?
Who reviews the flood elevation certification before a plat is approved?
Sources & Official References
Other rules in Taylor County
Texas rules heatmap·Compare Taylor County to another location·View the Texas environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.