Williamson County, TX Environmental Rules: Stormwater Management (2026)

Light Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Recharge Zone
WPAP required first
CGP Threshold
1 acre disturbed
Permanent Controls
Capture new pollutant load
Enforcement
TCEQ

Summary

Construction over the Edwards Aquifer recharge zone in western Williamson County requires a TCEQ-approved water pollution abatement plan under 30 TAC Chapter 213. Any site disturbing one acre or more also needs coverage under the TPDES Construction General Permit TXR150000.

City-specific rules exist: Cedar Park, and Round Rock have their own stormwater management rules that differ from Williamson County's county-level regulations. If you live in one of those cities, check the city-specific page instead.

Required plans. A plan must be submitted for the following, as appropriate: (1) a water pollution abatement plan under subsection (b) of this section to conduct regulated activities on the recharge zone not covered by subsections (c), (d), or (e) of this section.

Source: Texas StatutesView official code

Official source re-checked September 7, 2026: the cited page had not changed since it was quoted.

Full Breakdown

The recharge and contributing zones of the Edwards Aquifer run through western Williamson County, including areas around Georgetown, Cedar Park, and Leander. Regulated construction on the recharge zone must have a water pollution abatement plan approved by TCEQ before any land disturbance begins. Sites disturbing one acre or more must file a Notice of Intent for the TXR150000 Construction General Permit and keep a stormwater pollution prevention plan on site. Permanent water-quality controls must capture the increase in pollutant load from new impervious cover.

Violations & Fines

Clearing or excavating recharge-zone land without an approved water pollution abatement plan triggers TCEQ enforcement, administrative penalties, and stop-work orders. Discharging construction stormwater without Construction General Permit authorization violates the Texas Water Code.

Frequently Asked Questions

Does every construction site need a water pollution abatement plan?
Only regulated activities on the Edwards Aquifer recharge zone do. Sites off the recharge zone still need Construction General Permit coverage if they disturb one acre or more.
Who approves the water pollution abatement plan?
TCEQ reviews and approves it before construction starts. Technical review of an administratively complete application runs up to 90 days.

Sources & Official References

Other rules in Williamson County

All Williamson County rules

Texas rules heatmap·Compare Williamson County to another location·View the Texas environmental rules overview

Get notified when Stormwater Management in Williamson County, TX changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Stormwater Management in Cities Across Williamson County