Harrison County, MS Environmental Rules: Stormwater Management (2026)
Key Facts
- Governing office
- Harrison County Engineer
- Design storm
- 25-year, 24-hour rainfall event
- Overflow capacity required
- 100-year, 24-hour storm
- DMSP submittal fee
- None required
- Penalty
- $25-$250 fine, misdemeanor, per day
- Appeal window
- 30 days to Board of Supervisors
- Coverage
- Unincorporated Harrison County only
Summary
Harrison County's Drainage Management Site Plan Ordinance requires engineered stormwater controls for new development in the unincorporated county, capping post-development runoff at the pre-development release rate and routing every plan through the County Engineer before any building permit issues.
The purpose of this ordinance is to reduce or eliminate the hazards to the public health and safety caused by excessive Stormwater runoff, reduce economic losses to individuals and the community at large, and protect, conserve and promote the orderly development of land and water resources. The provisions of this ordinance further supplement ordinances and regulations as follows: a. Subdivision Regulations: For the unincorporated area of Harrison County b. Zoning Regulations: For the unincorporated area of Harrison County
Official source re-checked September 7, 2026: the cited page had not changed since it was quoted.
Full Breakdown
Adopted as UDC § 1012, the Drainage Management Site Plan Ordinance applies only to the unincorporated area of Harrison County: it supplements, rather than replaces, the county's separate Subdivision and Zoning Regulations, and it does not reach Gulfport, Biloxi, Long Beach, Pass Christian or D'Iberville, which administer their own drainage rules. A Drainage Management Site Plan (DMSP), sealed by a Mississippi-registered professional engineer, must model runoff for the 25-year, 24-hour storm and demonstrate that the controlled release rate from the site will not exceed the pre-development rate unless no significant downstream harm results.
Detention basins, culverts and channel sections must be sized against that standard, and an excess stormwater passage capable of carrying a 100-year, 24-hour event must be provided through every site, with no buildings permitted inside it. 02. 03 sets no fee for submitting the DMSP itself, though a separate, refundable Utility Permit fee applies to right-of-way encroachment work. Maintenance of stormwater improvements must be secured through a recorded maintenance agreement or covenant running with the property.
Violations & Fines
Noncompliance is enforced by the County Engineer or Harrison County Road Department through a written Notice of Violation listing every deficiency; the violator gets 10 days to correct them before a citation, Stop Work Order, or revocation of the Utility Permit and forfeiture of its bond can follow. Under § 1012.05.04, conviction is a misdemeanor carrying a fine of $25 to $250 and/or one day's imprisonment, with each day of continuing violation a separate offense. Decisions may be appealed to the Board of Supervisors within 30 days, though an appeal does not stay penalties for violations the County Engineer deems an immediate health or safety threat.
Frequently Asked Questions
Does this drainage ordinance cover property inside Gulfport or Biloxi?
Is there a fee to submit a Drainage Management Site Plan?
What runoff standard must a new development meet?
Who reviews and approves drainage plans in the county?
Sources & Official References
Other rules in Harrison County
Compare Harrison County to another location·View the Mississippi environmental rules overview