Key Facts

Governing office
Harrison County Engineer
Design storm
25-year, 24-hour rainfall event
Overflow capacity required
100-year, 24-hour storm
DMSP submittal fee
None required
Penalty
$25-$250 fine, misdemeanor, per day
Appeal window
30 days to Board of Supervisors
Coverage
Unincorporated Harrison County only

Summary

Harrison County's Drainage Management Site Plan Ordinance requires engineered stormwater controls for new development in the unincorporated county, capping post-development runoff at the pre-development release rate and routing every plan through the County Engineer before any building permit issues.

These county ordinances apply to unincorporated areas of Harrison County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

The purpose of this ordinance is to reduce or eliminate the hazards to the public health and safety caused by excessive Stormwater runoff, reduce economic losses to individuals and the community at large, and protect, conserve and promote the orderly development of land and water resources. The provisions of this ordinance further supplement ordinances and regulations as follows: a. Subdivision Regulations: For the unincorporated area of Harrison County b. Zoning Regulations: For the unincorporated area of Harrison County

View official code

Official source re-checked September 7, 2026: the cited page had not changed since it was quoted.

Full Breakdown

Adopted as UDC § 1012, the Drainage Management Site Plan Ordinance applies only to the unincorporated area of Harrison County: it supplements, rather than replaces, the county's separate Subdivision and Zoning Regulations, and it does not reach Gulfport, Biloxi, Long Beach, Pass Christian or D'Iberville, which administer their own drainage rules. A Drainage Management Site Plan (DMSP), sealed by a Mississippi-registered professional engineer, must model runoff for the 25-year, 24-hour storm and demonstrate that the controlled release rate from the site will not exceed the pre-development rate unless no significant downstream harm results.

Detention basins, culverts and channel sections must be sized against that standard, and an excess stormwater passage capable of carrying a 100-year, 24-hour event must be provided through every site, with no buildings permitted inside it. 02. 03 sets no fee for submitting the DMSP itself, though a separate, refundable Utility Permit fee applies to right-of-way encroachment work. Maintenance of stormwater improvements must be secured through a recorded maintenance agreement or covenant running with the property.

Violations & Fines

Noncompliance is enforced by the County Engineer or Harrison County Road Department through a written Notice of Violation listing every deficiency; the violator gets 10 days to correct them before a citation, Stop Work Order, or revocation of the Utility Permit and forfeiture of its bond can follow. Under § 1012.05.04, conviction is a misdemeanor carrying a fine of $25 to $250 and/or one day's imprisonment, with each day of continuing violation a separate offense. Decisions may be appealed to the Board of Supervisors within 30 days, though an appeal does not stay penalties for violations the County Engineer deems an immediate health or safety threat.

Frequently Asked Questions

Does this drainage ordinance cover property inside Gulfport or Biloxi?
No. UDC § 1012 governs only the unincorporated area of Harrison County; Gulfport, Biloxi, Long Beach, Pass Christian and D'Iberville enforce their own drainage rules for property inside their city limits.
Is there a fee to submit a Drainage Management Site Plan?
No. Section 1012.03.03 states there is no fee required with the submittal of the DMSP, though a separate, refundable Utility Permit fee set by the Board of Supervisors applies to any roadway entrance or right-of-way work.
What runoff standard must a new development meet?
The controlled release rate of stormwater leaving the site generally cannot exceed the pre-development rate, calculated for the 25-year, 24-hour storm, unless the developer shows no significant downstream harm will result; an excess stormwater passage sized for the 100-year storm is also required.
Who reviews and approves drainage plans in the county?
The Harrison County Engineer reviews and approves every DMSP and lesser plan; no final subdivision plat can be approved and no building permit issued until that approval is in hand.

Sources & Official References

Other rules in Harrison County

All Harrison County rules

Compare Harrison County to another location·View the Mississippi environmental rules overview

Get notified when Stormwater Management in Harrison County, MS changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.