Key Facts

Governing section
County Code § 34-78(k), Subdivision Regulations
Design storm
100-year frequency storm for flood levels
Reviewing body
Local soil and water conservation district
Off-site standard
No added sediment or erosion beyond baseline
Basin sizing
Sized for full drainage basin build-out
Linked requirement
Must also conform to Ch. 18 floodplain rules

Summary

New subdivisions in unincorporated Sandoval County must be designed and built so post-development runoff does not increase flooding or erosion, sized to the 100-year storm, and reviewed by the local soil and water conservation district before final plat approval.

These county ordinances apply to unincorporated areas of Sandoval County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

(k)Storm drainage plan.(1)Subdivisions and developments shall be planned, constructed and maintained to:a.Protect and preserve existing natural drainage channels except where erosion and water control measures are found necessary and approved by the local district.b.Provide temporary measures to prevent damaging runoff waters from leaving the site until construction is completed and permanent control measures are installed.c.Protect structures and other works from flood hazards using the 100-year frequency storm for calculating flood levels.d.Provide a system wherein runoff water within the subdivision is removed without causing harm or damage to the environment, property, or persons, inside or outside the subdivision area.e.Assure that water drained from the subdivision does not contain pollutants or sedimentary materials of any greater quantity than would occur in the absence of the subdivision.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 13).

Full Breakdown

Sec. 34-78(k), Storm drainage plan, requires that subdivisions and developments be planned, constructed and maintained to protect and preserve existing natural drainage channels except where erosion and water control measures are found necessary and approved by the local district. Developers must provide temporary measures to keep damaging runoff from leaving the site until construction is finished and permanent controls are installed, and must protect structures from flood hazards using the 100-year frequency storm to calculate flood levels. The system must remove runoff from within the subdivision without causing harm inside or outside its boundaries, and the county requires assurance that water leaving the site carries no more pollutants or sediment, and causes no more erosion, than would occur without the subdivision.

All storm drainage systems must be built to the standards of the local soil and water conservation district, and if the surrounding drainage basin is only partially developed, the district can require the system to be sized for the entire basin on the assumption it will eventually be fully built out. The plan must also address road drainage: ponding from road construction must be avoided or addressed, road-collected runoff must be designed to prevent erosion and sedimentation at outlets, and culverts must be properly sized, located and protected at their inlets and outlets.

Subsection (j) folds floodplain compliance into the same plan, requiring every subdivision to conform to the county's flood damage prevention ordinance in Chapter 18, tying the stormwater plan directly to the county's floodplain permit process.

Violations & Fines

A subdivision cannot receive final plat approval without a storm drainage plan meeting Sec. 34-78(k)'s standards; the county and the local soil and water conservation district review the plan, and the board of county commissioners can withhold or condition plat approval until the drainage design is adequate to prevent off-site flooding, erosion or sedimentation.

Frequently Asked Questions

What storm drainage standard applies to new subdivisions in Sandoval County?
Sec. 34-78(k) requires subdivisions to be planned, built and maintained so runoff is removed without harming property inside or outside the subdivision, sized to the 100-year frequency storm, and reviewed against the local soil and water conservation district's standards.
Can a developer just channel runoff onto neighboring land?
No. Sec. 34-78(k)(1)(e) and (f) require the developer to assure that water leaving the site carries no more pollutants or sediment, and causes no greater erosion, than would occur if the subdivision were never built.
Who reviews the storm drainage plan for a new subdivision?
The local soil and water conservation district sets the construction standards under Sec. 34-78(k)(2), and if the surrounding drainage basin is only partially developed, the district can require the system to be sized for the entire basin's eventual build-out.
Does the storm drainage plan cover road culverts too?
Yes. Sec. 34-78(k)(1)(g) requires roads collecting or discharging runoff to be designed to control erosion, culvert outlets into drainage courses to be protected against erosion, and culverts to be properly sized, located and protected at both inlets and outlets.

Sources & Official References

Other rules in Sandoval County

All Sandoval County rules

Compare Sandoval County to another location·View the New Mexico environmental rules overview

Get notified when Stormwater Management in Sandoval County, NM changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.