Taylor County, TX Environmental Rules: Stormwater Management (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Runoff cap
post-development peak cannot exceed pre-development peak
ROW ditch design storm
10-year rainfall frequency
Structures/culverts design storm
25-year flood frequency
Study required
registered professional engineer, every subdivision
Major creek crossings
frequency set by Commissioners' Court
Governing sections
Art. VIII §§8.01-8.07

Summary

Taylor County caps post-development storm water runoff at pre-development levels and sets the design storms subdivisions must build to. Article VIII requires an engineer's drainage study for every subdivision, 10-year-frequency roadside ditches, and 25-year-frequency culverts, bridges, and low-water crossings before the Commissioners' Court will accept the streets.

City-specific rules exist: Abilene has its own stormwater management rules that differ from Taylor County's county-level regulations. If you live in Abilene, check the city-specific page instead.

8.04 The peak discharge of storm water runoff, both within the subdivision and the outflow from the subdivision, must not exceed the peak discharge of the property in the undeveloped state. 8.05 All ROW ditches will be constructed using a 10-year rainfall frequency. All structures, culverts, bridges, low water crossings will be designed on a 25-year flood frequency. In a subdivision where the road crosses a major creek (i.e. Elm Creek, Jim Ned, and others), the design frequency will be determined by the Commissioners’ Court.

Full Breakdown

Article VIII, DRAINAGE, requires every subdivision proposal to provide adequate drainage to reduce flood exposure and to size lots so they still leave room to build. 01 requires a registered professional engineer to study both interior and exterior storm water runoff and to document conveyances, easements, base flood elevation data, and finished floor elevations, plus culverts, bridges, and other site-specific features. 04 sets the core performance standard: the peak discharge of storm water runoff, both within the subdivision and the outflow from the subdivision, must not exceed the peak discharge of the property in the undeveloped state, meaning new development cannot dump more water onto neighboring land than the raw land did before.

05 sets the design storms: right-of-way ditches are built to a 10-year rainfall frequency, while structures, culverts, bridges, and low-water crossings are designed to a 25-year flood frequency; where a subdivision road crosses a major creek such as Elm Creek or Jim Ned, the Commissioners' Court sets the design frequency itself. 07 requires an engineer's letter, with as-built drawings, recommending acceptance before the Commissioners' Court will take over the streets and drainage work. 02 lets a subdivision with limited drainage problems narrow the study's scope, but the engineer's report must still show the full range of requirements was considered.

Violations & Fines

A plat that skips the engineer's drainage study, exceeds the pre-development peak discharge cap in § 8.04, or under-designs ditches and culverts below the 10-year and 25-year frequencies in § 8.05 will not clear final engineering certification under § 8.06, and the Commissioners' Court can refuse to accept the streets and drainage improvements under § 8.07 until the as-built work is corrected.

Frequently Asked Questions

Can a new subdivision in Taylor County increase runoff onto neighboring land?
No. Article VIII § 8.04 requires the peak discharge of storm water runoff, both within and leaving the subdivision, to not exceed the peak discharge the property produced in its undeveloped state, so the drainage design must offset whatever the new lots and streets add.
What storm frequency do Taylor County culverts have to handle?
Article VIII § 8.05 designs structures, culverts, bridges, and low-water crossings to a 25-year flood frequency, while right-of-way ditches are built to a 10-year rainfall frequency. Crossings of major creeks like Elm Creek or Jim Ned get a frequency set directly by the Commissioners' Court.
Who signs off on a subdivision's drainage work before the county takes it over?
The project engineer must certify under § 8.06 that every Article VIII drainage requirement has been met, then submit a letter with as-built drawings under § 8.07 recommending acceptance before the Commissioners' Court will accept the streets and drainage improvements into the county system.

Sources & Official References

Other rules in Taylor County

All Taylor County rules

Texas rules heatmap·Compare Taylor County to another location·View the Texas environmental rules overview

Get notified when Stormwater Management in Taylor County, TX changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Stormwater Management in Cities Across Taylor County