Sandoval County, NM Fence Regulations: Retaining Walls (2026)
Key Facts
- Permit trigger
- Any retaining wall, no height exemption
- Required plan
- Wall/foundation plan, NM engineer/architect-stamped
- Additional submittal
- Site plan
- Reviewing official
- Zoning Officer
- Code definition
- Self-standing structure for bank retention
- Violation fine
- Up to $300
Summary
Every retaining wall in Sandoval County needs a Zoning Officer building permit, with no minimum height exempting it. The application must include a site plan plus a wall and foundation plan stamped by a New Mexico registered engineer or architect before the county will approve construction.
G.Building Permits. Building permits, applications for building permits, and certificates of occupancy within the County's zoning jurisdiction shall be considered by the Zoning Officer upon submission of appropriate construction plans, accompanying materials as specified in Section 15(G)(1) of this Ordinance, and the required fee. Approval shall be granted only if same are found to be in compliance with the provisions of this Ordinance... [f.]Retaining Walls.1.Building Permit application from the appropriate authority.2.Site Plan.3.Wall/foundation plan stamped by a New Mexico Registered Engineer or Architect.
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 13).
Full Breakdown
Retaining walls fall under the same Building Permit checklist as fencing, foundations, and new construction in Section 15(G)(2) of the Comprehensive Zoning Ordinance, but the county holds them to a stricter bar. Section 15(G)(2)(f) requires, for any retaining wall project, a building permit application filed with the Zoning Officer, a site plan, and a wall/foundation plan stamped by a New Mexico Registered Engineer or Architect, regardless of the wall's height; unlike the fencing rule, which only kicks in above six feet, there is no height floor before the retaining-wall permit and engineering-stamp requirement applies.
The ordinance's definitions section separately describes "Fences," "Screen walls," or "Retaining walls" as self-standing structures built to provide semi-privacy, security, or bank retention between grade separations, distinguishing retaining walls from ordinary decorative walls by their structural, grade-holding function. Because the Zoning Officer reviews all Section 15(G) submittals for compliance before issuing a permit, an incomplete application, one missing the stamped engineering plan, will not be accepted. Sign permit applications for freestanding structures exceeding 20 feet also require a similarly stamped engineer's design under the sign regulations, showing the county applies the same structural-safety standard to any tall, freestanding built feature on a property, retaining wall or otherwise.
Violations & Fines
Building a retaining wall without the required permit, site plan, and stamped engineer or architect drawing violates the Zoning Ordinance's Building Permit requirements and is enforceable under Section 24: the Zoning Officer can cite the property owner or builder, with fines capped at $300 per violation and any county remediation costs added as a debt collectible by lien.
Frequently Asked Questions
Does a short retaining wall still need an engineer's stamp?
What's the difference between the retaining wall rule and the fence rule?
Who can stamp my retaining wall plans?
Sources & Official References
Other rules in Sandoval County
Compare Sandoval County to another location·View the New Mexico fence regulations overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.