Key Facts

Grading permit threshold
Over 50 cubic yards, Sec. 13-3
Setback, slopes 0-10 ft
5 feet from cut/fill edge
Setback, slopes over 30 ft
15 feet from cut/fill edge
Engineer's plans required
Cuts/fills over 15 ft or 10,000 cu yd
Max slope without engineering
1:1 cuts, 1.5:1 fills
Enforcing agency
Director of Public Works

Summary

Butte County's grading ordinance treats retaining walls as an engineering tool for meeting cut-and-fill setbacks, not as a routine fence. Section 13-11(d) sets a sliding setback from the top of any cut or the toe of any fill, from five feet for slopes up to ten feet high to fifteen feet for slopes over thirty feet, but lets the Director of Public Works approve a retaining wall or deep foundation to shrink that distance.

City-specific rules exist: Chico has its own retaining walls rules that differ from Butte County's county-level regulations. If you live in Chico, check the city-specific page instead.

The setbacks specified by this section are minimum requirements and may be increased by the director or by the recommendation of a civil engineer, soils engineer or engineering geologist, if necessary for safety and stability, or to prevent damage to other properties, structures, channels, and roadways from deposition or erosion, or provide access for slope maintenance and drainage. Retaining walls and/or deep foundations may be used to reduce the required setbacks when approved by the director.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 61).

Full Breakdown

Section 13-2 defines 'fence' to specifically exclude retaining walls, so retaining walls fall under the grading rules in Chapter 13 rather than the wall-and-fence design standards in Chapter 24. Section 13-3 requires a grading permit for any earth movement over fifty cubic yards, and Section 13-11(d)(2) sets the baseline setbacks any grading project must keep from the top of a cut or the toe of a fill: five feet for slope heights up to ten feet, half the slope height for slopes between ten and thirty feet, and fifteen feet for anything taller.

The same subsection lets the director, or a recommending civil engineer, soils engineer or engineering geologist, increase those setbacks where needed for slope stability or to protect neighboring structures and roadways, and it expressly authorizes retaining walls or deep foundations as a way to reduce the required setback instead. Section 13-6(b)(10) requires a full engineering plan, soils report and erosion control plan stamped by a licensed civil engineer whenever total cut and fill exceeds ten thousand cubic yards, or when any single cut or fill exceeds fifteen feet in height, or the existing slope exceeds twenty percent grade, standards that capture most substantial retaining wall projects.

Section 13-11(f)(1) additionally caps slope steepness at one-to-one for cuts and one-and-a-half-to-one for fills unless a retaining structure or a geotechnical analysis justifies something steeper.

Violations & Fines

Grading more than fifty cubic yards, including the cut or fill a retaining wall supports, without the required permit is chargeable as an infraction under Section 13-3, punishable per Section 41-5 pursuant to the cross-reference in Section 1-7(b). The Director of Public Works can also require corrective grading or a financial assurance bond under Section 13-12 if work isn't completed to the approved plans, and an unapproved wall built without the engineering plans and soils report required for larger projects can be ordered removed or re-engineered.

Frequently Asked Questions

Does Butte County regulate retaining walls the same as fences?
No. Section 13-2 of the grading ordinance specifically excludes retaining walls from the definition of 'fence,' so they're governed by Chapter 13's grading and setback rules rather than the fence height and design standards in Chapter 24.
How far must a retaining wall sit from my property's cut or fill edge?
Section 13-11(d)(2) sets a sliding setback: five feet for slopes up to ten feet high, half the slope height for slopes between ten and thirty feet, and fifteen feet for anything taller, though the Director of Public Works can require more for stability.
Can a retaining wall reduce my required grading setback?
Yes. Section 13-11(d)(2) expressly allows the Director of Public Works to approve a retaining wall or deep foundation as a way to shrink the standard cut-and-fill setback, provided it's justified for safety and stability.
When does a Butte County retaining wall need an engineer's stamp?
Section 13-6(b)(10) requires engineering plans, a soils report and an erosion control plan signed by a licensed civil engineer once total cut and fill exceeds 10,000 cubic yards, or when any cut or fill exceeds 15 feet, or the existing slope exceeds 20 percent.

Sources & Official References

Other rules in Butte County

All Butte County rules

California rules heatmap·Compare Butte County to another location·View the California fence regulations overview

Get notified when Retaining Walls in Butte County, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Retaining Walls in Cities Across Butte County