Monterey County, CA Parking Rules: EV Charging (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Applies to
Unincorporated Monterey County only
Permit type
Nondiscretionary construction permit
Use permit trigger
Specific, adverse safety impact
Review standard
Health & safety compliance only
Appeal body
County Planning Commission
Adopted
Ord. No. 5275, September 13, 2016

Summary

In unincorporated Monterey County, installing an electric vehicle charging station requires a construction permit processed through an expedited, nondiscretionary review under Monterey County Code § 18.18.020. The Building Official checks only health and safety compliance; a discretionary use permit kicks in solely if staff finds a specific, adverse safety impact with no feasible fix. Routine maintenance and pre-2016 stations are exempt.

City-specific rules exist: Salinas has its own ev charging rules that differ from Monterey County's county-level regulations. If you live in Salinas, check the city-specific page instead.

A.This Chapter applies to the permitting of all electric vehicle charging stations, as defined, in the unincorporated area of the County of Monterey.B.A construction permit is required to install utility interconnected electric vehicle charging stations.C.Electric vehicle charging stations legally established or permitted prior to the effective date of Ordinance No. 5275 enacting this Chapter are not subject to the requirements of this Chapter unless physical modifications or alterations are undertaken that materially change the size, type, or components of an electric vehicle charging station in such a way as to require new permitting. Routine operation and maintenance shall not require a permit.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 56).

Full Breakdown

18, adopted by Ord. No. 7, applies only to charging stations in the unincorporated area of the County; Salinas, Monterey, Seaside, Marina, Carmel-by-the-Sea, Pacific Grove and King City run their own building departments and are not covered. A construction permit is required for any utility-interconnected charging station, but stations legally installed before the ordinance's effective date are grandfathered unless they undergo physical modifications that materially change size, type or components. Applications may be submitted electronically, including electronic signatures in lieu of a wet signature. The Building Official must develop a checklist substantially conforming to the Plug-In Electric Vehicle Infrastructure Permitting Checklist in the Governor's Office of Planning and Research's Zero-Emission Vehicles in California guidebook, and applications meeting that checklist are administratively approved as nondiscretionary permits within a reasonable time once fees are paid.

Review is limited to whether the station meets local, state and federal health and safety law; local standards may not exceed what is necessary to avoid a 'specific, adverse impact' on public health or safety. If the Building Official, in consultation with the Chief of Planning, finds such an impact based on substantial evidence, the applicant must instead apply for a discretionary use permit, and that requirement can be appealed to the County Planning Commission. A use permit itself may only be denied on written findings of a specific, adverse impact with no feasible mitigation, and that denial is appealable to the Planning Commission or, if the Commission was the decision-maker, to the Board of Supervisors. Stations must also meet California Electrical Code Article 625 and applicable Public Utilities Commission safety standards. 40.

Violations & Fines

Installing a utility-interconnected charging station without the required construction permit is unpermitted electrical work, enforceable through the County's standard building permit process rather than a chapter-specific fine. If the Building Official requires a use permit and the applicant proceeds without one, the installation is not authorized under Chapter 18.18. A use permit denial or a decision requiring one can be appealed to the County Planning Commission within the timelines set by County appeal procedures; the Board of Supervisors hears further appeals when the Commission was the original decision-maker.

Frequently Asked Questions

Do I need a permit for a home EV charger in unincorporated Monterey County?
Yes. Monterey County Code § 18.18.020 requires a construction permit for any utility-interconnected electric vehicle charging station, but the Building Official must process it as a nondiscretionary, expedited permit once your application meets the county's checklist and fees are paid.
Can the county deny my EV charging station application?
Only in a limited way. The Building Official can require a discretionary use permit if there is substantial evidence of a specific, adverse health or safety impact, and that use permit can be denied only with written findings that no feasible mitigation exists; you can appeal to the Planning Commission.
Does this permit rule apply in Monterey or Salinas?
No. Chapter 18.18 applies only to the unincorporated area of Monterey County. Salinas, Monterey, Seaside, Marina, Carmel-by-the-Sea, Pacific Grove and King City are incorporated cities with their own building departments and permitting rules.

Sources & Official References

Other rules in Monterey County

All Monterey County rules

California rules heatmap·Compare Monterey County to another location·View the California parking rules overview

Get notified when EV Charging in Monterey County, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.