Summary
El Dorado County runs an expedited, ministerial permit process for home and commercial EV charging stations under Chapter 110.70, following state law AB 1236. The Building Official can only demand a conditional use permit if the station poses a specific, documented safety impact.
This chapter applies to the permitting of all electric vehicle charging stations within the unincorporated area of the County of El Dorado... The Building Official, consistent with Government Code § 65850.7, shall not condition the approval of an application on the approval of an association, as Civil Code § 4080 defines that term... The Building Official may require an applicant to apply for a conditional use permit if the Building Official makes a written finding, based on substantial evidence, that the proposed electric vehicle charging station could have a specific, adverse impact upon the public health or safety.
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 13 Update 4).
Full Breakdown
70, adopted by Ordinance No. 5165 in 2022, applies to permitting of all electric vehicle charging stations in unincorporated El Dorado County, exempting stations already legally installed unless they are later physically modified enough to require new permitting. Before applying, an installer must verify the station will not create a specific, adverse impact on public health, safety, or building occupants, covering electrical system capacity and loads, wiring, bonding and overcurrent protection, affected building infrastructure, and the charging and parking area. An application meeting the County's adopted EV Checklist is deemed complete and processed promptly; the Building Official reviews it as a ministerial, ordinary permit limited to local, state, and federal health and safety requirements, and cannot condition approval on an association's approval under Civil Code Section 4080.
Approval alone does not authorize energizing the station until final building permit approval is granted. 090. Installed equipment must meet the California Electrical Code and be incorporated into the load calculations for the property's electrical service as a continuous load, and floor- or wall-mounted stations must meet the anchorage requirements of the California Building or Residential Code and the manufacturer's instructions.
Violations & Fines
An incomplete permit application draws a correction notice from the Building Official detailing the deficiencies rather than an outright denial. Energizing or using a charging station before final building permit approval, or installing one without meeting the California Electrical Code load and anchorage requirements, is enforceable as a building code violation subject to the County's standard misdemeanor penalty of up to $1,000.00 or six months in jail under Section 110.16.020(C).
Frequently Asked Questions
Do I need a special permit to install a home EV charger in El Dorado County?
Can my HOA block my EV charging station permit?
When can the County require a conditional use permit instead?
Sources & Official References
Other rules in El Dorado County
California rules heatmap·Compare El Dorado County to another location·View the California parking rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.