Placer County, CA Parking Rules: EV Charging (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified August 2026

Key Facts

Deemed-complete window
5 business days (10 if >25 stations)
Deemed-approved window
20 business days (40 if >25 stations)
HOA approval
Cannot be required absent safety finding
Appeal body
Planning commission / Building Board of Appeals
Appeal window
30 days from building official's decision
Governing statute
Implements Gov. Code § 65850.7

Summary

Placer County Code § 15.04.160 sets an expedited, deemed-approved permit process for electric vehicle charging stations. An application is deemed complete after five business days (10 for more than 25 stations at one site) without a correction notice, and deemed approved, with all permits issued, after 20 business days (40 for more than 25 stations) unless the building official finds a specific adverse health or safety impact.

City-specific rules exist: Roseville has its own ev charging rules that differ from Placer County's county-level regulations. If you live in Roseville, check the city-specific page instead.

"Electric vehicle charging station" or "charging station" means any level of electric vehicle supply equipment station that is designed and built in compliance with Article 625 of the California Electrical Code, as it reads on the effective date of this chapter, and delivers electricity from a source outside an electric vehicle into a plug-in electric vehicle... Twenty business days after the application was deemed complete, if the application is for at least 1, but not more than 25 electric vehicle charging stations at a single site. Forty business days after the application was deemed complete, if the application is for more than 25 electric vehicle charging stations at a single site.

Full Breakdown

160 requires the building official to run an expedited administrative review for any electric vehicle supply equipment built to Article 625 of the California Electrical Code that delivers power into a plug-in vehicle. The county must publish an adopted checklist on its website, accept electronic submittals including e-mail, internet, or fax, and take electronic signatures. An application is deemed complete once five business days pass (10 business days for more than 25 charging stations at one site) without the building official either deeming it complete or issuing a written correction notice detailing every deficiency.

Once complete, the application is deemed approved and all necessary permits issue automatically after 20 business days (40 business days for more than 25 stations) unless the building official has affirmatively approved it, found based on substantial evidence that the installation could have a specific adverse impact on public health or safety, or denied it because no feasible mitigation exists; an appeal to the planning commission also pauses deemed approval. The building official cannot condition approval on a homeowners' association's sign-off unless that same adverse-impact finding is made.

A building official's decision may be appealed to the Building Board of Appeals within 30 days. Approval of the permit itself does not authorize energizing the station: separate authorization from the county is still required before use.

Violations & Fines

Energizing or using an approved electric vehicle charging station before the county grants separate authorization to do so is not permitted under § 15.04.160(F)(4)(c). Because the underlying installation is regulated as electrical work, unpermitted charging stations fall under the building code's general violation provisions in § 15.04.140: a misdemeanor (or infraction for a first offense under County Code § 1.24.010), with each day of continued violation a separate offense.

Frequently Asked Questions

How long does Placer County take to approve an EV charging station permit?
Under § 15.04.160, an application for 25 or fewer stations at one site is deemed complete after 5 business days and deemed approved, with permits automatically issued, after 20 business days, unless the building official acts sooner or finds a specific adverse safety impact.
Can my homeowners' association block my EV charger permit?
No. The building official cannot condition permit approval on association approval unless the county finds, based on substantial evidence, that the charging station could have a specific adverse impact on public health or safety.
Can I use my EV charger as soon as the permit is approved?
No. Permit approval under § 15.04.160(F)(4)(c) does not authorize energizing or using the station; separate county authorization is required before it can be connected and used.

Sources & Official References

Other rules in Placer County

All Placer County rules

California rules heatmap·Compare Placer County to another location·View the California parking rules overview

Get notified when EV Charging in Placer County, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

EV Charging in Cities Across Placer County