Kitsap County, WA Parking Rules: EV Charging (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Applies to
New construction; redevelopment >=50% of assessed value
Required ratio
1 EV space per 10 standard parking spaces
Accessible share
10% of EV spaces, minimum of one
Minimum charger level
Level 2 (208 or 240 volts)
Adopted
Ordinance 620, 2023

Summary

New construction and major redevelopment in unincorporated Kitsap County must provide one Level 2 electric vehicle charging space for every ten standard parking spaces under KCC § 17.490.080, with 10 percent of those spaces made accessible.

These county ordinances apply to unincorporated areas of Kitsap County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

A. Minimum Standards for Electric Vehicle Charging Spaces. Standards shall apply to all new construction, and to redevelopment projects where the project cost is fifty percent or more of the assessed value of the buildings. 1. One electric vehicle charging space is required for every ten standard vehicle parking spaces required, rounded up. Ten percent of the electric vehicle charging spaces shall be accessible parking spaces, rounded up, with a minimum of one required... 3. Electric vehicle charging stations shall be at least Level 2 chargers: two hundred eight or two hundred forty volts. 4. Electric vehicle charging spaces are reserved solely for charging of electric vehicles. Vehicles that are no longer charging should be relocated to a standard vehicle parking space. Signage to this effect shall be posted.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: rev 4864424; v0 updated 2025-12-08; through 12-08-2025).

Full Breakdown

080 sets minimum electric vehicle charging standards that apply to all new construction and to redevelopment projects where the project cost equals 50 percent or more of the assessed value of the existing buildings. Subsection A requires one EV charging space for every ten standard vehicle parking spaces required on the site, rounded up, and requires 10 percent of those EV spaces (with a minimum of one) to be accessible parking spaces. 04, and the stations themselves must be at least Level 2 chargers, rated at 208 or 240 volts.

EV spaces are reserved solely for charging; a vehicle that is no longer charging must be relocated to a standard space, and the site must post signage saying so. 040, except accessible charging spaces, which follow the building code's accessible parking dimensions. Site lighting must illuminate any EV charging spaces available for use outside daytime hours, and the operator's contact information must be posted on the charging equipment for reporting malfunctions. Subsection B lets a developer reduce required non-EV vehicle parking by 5 percent for each of several EV-related upgrades: installing Level 3 (480-volt) 'fast' chargers instead of Level 2; providing one EV space for every five required stalls instead of every ten; or, on sites with 250 or more required stalls, installing one EV space sized for a passenger truck towing a trailer (a pull-through or double-length stall with the charger mounted to the side).

These standards were adopted by Ordinance 620 in 2023 and apply only in unincorporated Kitsap County; Bremerton, Port Orchard, Poulsbo, and Bainbridge Island each set their own EV parking requirements under separate city codes.

Violations & Fines

A site plan or building permit that omits the required EV charging ratio, installs chargers below Level 2 (208/240 volts), or fails to reserve and sign EV spaces as charging-only under § 17.490.080(A)(4) does not meet Kitsap County's development standards and can be denied, conditioned, or flagged in code compliance review by the Department of Community Development. Non-charging vehicles parked in a reserved EV space, or EV spaces built without the required posted operator contact information, are noncompliant with the posted signage and equipment-labeling requirements of the section.

Frequently Asked Questions

How many EV charging spaces does Kitsap County require?
KCC § 17.490.080(A)(1) requires one electric vehicle charging space for every ten standard vehicle parking spaces required on a project, rounded up, with 10 percent of those EV spaces made accessible.
What charger level does Kitsap County require at new EV parking spaces?
Section 17.490.080(A)(3) requires EV charging stations to be at least Level 2 chargers, rated at 208 or 240 volts; Level 3 'fast' chargers at 480 volts can be used instead to earn a parking reduction.
Can a gas-powered car park in a Kitsap County EV charging space?
No. Section 17.490.080(A)(4) reserves EV charging spaces solely for charging electric vehicles; a vehicle that is no longer charging must be relocated to a standard space, and the site must post signage stating this rule.

Sources & Official References

Other rules in Kitsap County

All Kitsap County rules

Compare Kitsap County to another location·View the Washington parking rules overview

Get notified when EV Charging in Kitsap County, WA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.